Sunset House, Cihei – Update & Gallery – August 1st, 2022
It is four months now since we ‘broke ground’ and dedicated this amazing project into God’s Hands for the future. And He is blessing us and the project in marvellous ways. Construction started in earnest 3 months ago, and it has amazed me how much time and effort is invested in the ground, providing a foundation upon which we can move forward to build this incredible facility to God’s Glory here in Romania. I am so pleased we have photographs to provide the memory, because very soon now, none of these foundations will be seen, as all will be covered in concrete within the next month!
You will see from viewing the updates month by month, the progress being made. This month you can see the second half of the building has had foundation below ground completed and filled with concrete. Metal strengthening is now being prepared for the entire site, and once the work is ‘signed off’ by the State Engineering Inspectors, tonnes of more concrete will be poured, covering everything we currently see, and creating what we call the Slab. Upon that slab, the building will begin to be built and how exciting will that stage be, which will no doubt begin in September.
Also, during August, a lot of plumbing pipes will be installed for the 38 bathrooms, kitchen, laundry and other facilities requiring underground piping and drainage. All the underground work will be completed before the concrete is poured. I can’t wait to share the pictures with you as progress is made.
I couldn’t help but be inspired during the foundation process and be reminded of how important foundations are, not only for a building, but also in life. So much of Smiles work is helping to build better foundations in the lives of people who struggle with all sorts of challenges. Now we trust the Contractor to do the same for our Sunset House, Cihei.

Many men are involved on site every day. I’m surprised just how intensive the work is even with the metal work. Many men diligently working on getting the levels exactly right, before tied into position awaiting the concrete.
I’ve decided to ask the Contractor just how much steel and concrete will have been used in the foundations which I’ll share with you when I get the details. I’m sure it will be staggering!
Sunset House, Cihei is the first facility Smiles has built that has really been possible for me to see, day by day.
Out of my office across the corridor, allows me to see the entire site from a window or the balcony. Our other key sites in Tileagd, Mierlau, Salonta, Arpasel all required journeys, sometimes an hour from the office, and with so much work to be attended to, I could never spend so much time checking on the detail of the job under construction. I’m not so sure it is great for the Construction company or site workers, but I am certainly delighted to be seeing the work undertaken all day, every day – even when cement trucks wake me up at 6am to pour during the hot summer!


The summer has certainly been hot, and whilst the dry weather has no doubt helped the construction to progress daily without delay, often the extreme heat meant days had to start early, often on site by 6am, taking a break from about midday to 5pm and then start again in the evening, often working until 8 or 9 at night. I’ve been delighted to see the professional approach to the task and sincerely pray it will continue through out the process of building Sunset House, Cihei.
As we reach the end of another month, I’ll leave you with a few pictures taken on site Thursday, July 28th.

When you see the site plan against our current Office Building, the size of Sunset House is obvious!
I also managed to make another short Video updating progress with Sunset House. I hope you’ll enjoy and be able to share it with friends and family to encourage them to be a part of this most recent of Miracles in Progress, for which we give thanks to God and ask for His continued blessings.
Keep in touch and continue to marvel at all that is happening here in Cihei, Romania with the Smiles Foundation.
Kevin D. Hoy
Founder and Chief Executive