Sunset House, Cihei: Update & Gallery, April 1st, 2023
How thrilled we all are when Spring arrives. So many beautiful signs of new life along with milder and warmer weather! Well all this is true for Smiles in Romania, but this year, we have an added reason to celebrate Spring. Work on Sunset House can progress faster, with less delays due to wintery conditions, so we now start seeing great progress on many different aspects of the construction challenge.
This past month, I have been in America for every day, but have managed to keep in touch, just about ‘every day’ through Site Cameras and Pictures received from Maria and Adi as progress was made on this exciting project.
Whilst I was hoping it could have been done while I was still in Romania back in February, the upper level slab of phase 2 was not ultimately poured until March 3rd. But how thrilling is was for me to see it done allowing the drying process to start so that supports could be removed after the alloted 21 days – allowing the next stage of construction to begin. 
So, March was off to a good start with this strategic stage reached to allow the upper level to have work started in the coming month.
While the cement was hardening and the 21 days passed before supports could be removed, work was focused at more walls on the upper level of phase one, and then, interior work started in earnest.
It was great to see the shape of the interior forming and the rooms were becoming more distinguishable.

Phase 2 was largely out of action for a few weeks while concrete hardened, but one of the benefits in doing this project in two parts, meant we could progress full steam ahead on phase 1 and with being such a large facility, no one seemed to be getting in the way … plenty of space to work for everyone!
So, it felt like everyone arrived at once!! Electricians, Plumbers, the Fire Safety Installation company, and Data Installations all seemed to be happening at the same time. If they hadn’t completely known ‘what they were doing’ it would have been a complete chaotic nightmare! But it wasn’t. Thanks be to God for having extremely professional teams on this project, making the whole experience so much more manageable than some of our previous adventures!
Electricians, Plumbers and Plasterers all start their first fixes.
As we drew closer to the end of March, the significant stage of interior plastering started as first fix for electrics and plumbing were complete in several rooms of ground level phase one. It’s a really nice stage to reach.
Plastering feels like a finishing stage of any new build. There is of course still a lot to do, but seeing plastered walls is so much better than bare brick!
Here the Plasterers are preparing for the huge job!
We will see during April, the walls on the upper level of phase 2 being built and significant progress with phase 1 in all aspects. So we have an exciting month ahead and I look forward to being back in Romania to see it all for myself.
What about you? Wouldn’t you like to see Sunset House face to face? Come on a Mission Trip or sign up for a Construction Special and you can be part of the magnificent journey we are experiencing through the construction of this wonderful facility.
We’ve been greatly encouraged recently by God’s Goodness in provision of significant funds, but we continue to need God’s Provision towards the Budget for this huge project.
Please continue to pray for us to be able to meet all the obligations coming up in the months ahead and do help wherever you can with a special gift for Sunset House.
Financial Commitments needing to be met soon are as follows:
£156,068 ($187,281) by April 30th, 2023. Then, £191,617 ($229,940) Payments in May 2023.
Please continue to pray and consider how you can help with this God-Sized miracle becoming the reality we believe it can be. All part of God’s Plan – all for His Glory, here in Romania.
Whether Donation, Grant or a Loan – all is helpful, appreciated and significant, whatever the amount might be. If I can answer any questions for you, please just contact me by e-mail or a message to the Smiles Office. I’ll get back to you as quickly as I can.
By the end of April, I will hopefully manage to record another video, showing the progress in the coming weeks. I greatly look forward to sharing next month’s update.
My sincere thanks for your interest and support for this incredible project.

Kevin D. Hoy