Sunset House, Cihei: Update & Gallery, August 1st, 2023
July has been a very challenging, stressful and difficult month with Sunset House construction. Whilst some progress has been made, and July got off to a reasonable start, we hit some major unexpected problems, which climaxed in the middle of a very busy Mission Trip and shocked everyone involved in the management of Sunset House, Cihei.
As a result of the delays experienced which obviously has implications on those responsible, tensions began to mount between the Main Contractor and the Sub-Contractor. Smiles contract is with the main contractor and he in turn contracts with various sub-contractors who we have no direct dealings with. But we certainly began to understand some major disagreement had arisen, when on July 19th, the entire work force of the Main Structure walked off site and never came back – at that point, we certainly knew a major problem existed! Since that day, the extreme pressures on all those involved, just grew and grew.
The main contractor was attempting to find a new crew, in the middle of the busy summer, when construction work is at its greatest demand. And, to take over a job part completed by another crew, was not an easy task!!
Meanwhile, I was attempting to manage ‘damage limitation’ to the broader issues of projects that were not only instantly affected, but the many that would have serious delays and implications in the weeks and potentially months to follow. It has taken many stressful days and some ‘intense discussions’ – other wise known as full-blown arguments – to reach a successful point, which we did only this morning (July 31st).
The Main Contractor had located a new team who start August 1st to continue the work not touched since July 19th. Various proposals for reassigning work on the interior which I had suggested 2 weeks ago, were finally accepted, and work on those issues will begin in earnest August 1st also. There is little chance, of the lost time being recovered, but my concern is to get all aspects back to work so the project is back on track, but until the new teams take up the work, it is virtually impossible at this stage to assess the overall impact the crisis will have on the deadline to finish. Personally, I anticipate the lost 2 weeks in July could add another month beyond the revised deadline for the finished main construction, so we could now be looking at October 1st, 2023.
All very frustrating and certainly quite stressful, but God is in Control, that we never doubt, so having dealt with the problems of July, we look forward to August being more productive.
Even while these problems were involving the main construction, particularly the Roof of Phase Two, many other teams were doing their work and some significant progress has been seen this past month.
When I left you on July 1st, we were hard at work to complete the preparations for Phase Two Roof, with steel reinforcement so that the cement slab could be poured. This was to be a major step towards the critically important task of ‘sealing’ the Roof and thereby avoid rain continnually seeping through the building making it hard for walls and floors to dry for Plastering, Painting and eventually, Flooring. 
All was moving forward well at the beginning of the month, so everything on the roof was ready for July 14th, when the cement trucks arrived once again for the big pour.


This was such a hot week with strong sun, after the concrete was poured, it was drying so quick, we had to be watering the entire surface, morning, noon and night to stop major cracking, but it was done and the finish was looking very good indeed.
The aerial view from our drone now showed the entire building with a slabbed roof, and it looked wonderful but was another reminder, just how large this building is!
Just compare it against our office building to the right or the Mission Centre at the top.
Turning to the interior, I was delighted the hot summer days were helping to dry the rooms on the lower level of Phase One, where we wanted to continue the painting process. Thankfully, that worked out and the start our Mission team had made in June was possible to continue in July.
Teams from Northern Ireland helped prime newly plastered walls and then undercoat, so by July 22nd all possible rooms were done to the undercoat stage.
A couple of the rooms could not be started yet due to their proximity to areas still exposed to the elements, particularly rain, so we had to hold off those rooms until more protection is available.
But the teams once again did a fantastic job and seeing 27 rooms completed as well as long corridors, was a very encouraging sight.
While our Teams were hard at work on the lower level, contractors were busy on the upper level with a considerable amount of 1st Fix Electrics. A very dirty, dusty job and in that heat, couldn’t have been easy or very pleasant, but they are making good progress and will be clear by the end of first week in August, for the Plasterers to come in for their first fix work.

Also, upper level of Phase One needed Bathroom Walls built in the Bedrooms, before Plasterers could start their first fix. To be honest, it has felt like we were asking for the world to have a few small walls built, the contractors just never seemed to get around to it, but that was holding up the plastering, so very frustrating.
So, with my heavy big foot going down again, and Walls started being built. Today, we are just a day or two from them all completed … another 13 rooms finished with block work. Praise God.
Back to the exterior, there is of course a lot of work to be done. Grounds, Roads, Landscaping etc will largely be thought about in the new year and whenever the weather allows us to start work on those projects, we will.
But there is also a lot of work related to the exterior of the main construction and great work was done during July on Insulating the Exterior Block work. 15cm (6 inch) polystyrene blocks provide an excellent insulation for the entire building. Helping to keep it warm in winter, but also cooler in the summer.
A good investment that will save multiple times its cost on Heating & Cooling expense in the years to come when Sunset House is operating.
The Insulation certainly starts to give a more finished look to the exterior. Of course, there is still painting of the exterior to be undertaken, but that will be a final task when a lot more of the construction work is done, limiting the dust and dirt around which we woudn’t want to cover our newly painted building!
So, a mixed month of highs and lows, but August is a new month, and we pray for a much smoother period at Sunset House. A new Mission team arrive on August 5th and then every week until September 9th, so hopefully some more painting and electrical installations will be done by our teams and possibly even more, with Tile/Slab laying on the Balconies being on my list if we can be ready when capable people are here to help.
My sincere thanks for your continued interest and support for this incredible project. Please continue praying for and supporting Sunset House, by every means you can. Thank you.

Kevin D. Hoy
Founder and Chief Executive
The Smiles Foundation