Sunset House, Cihei: Update & Gallery, December 1st, 2022

Sunset House Donate $Sunset House Donate £

As winter starts to be felt more and more, day by day, several days were lost in November due to weather and particularly rain. However, on the dry, bright days, the work crews progressed well and considerable progress was made with technical preparations for pouring the first floor slab on phase one of the building. Structural metal work was prepared on phase two and bricks were ready to start the walls imminently. We hope to see both these areas of work started in early December.

Sunset House progressAt the beginning of November, we started to prepare phase two of the building for the all important ground slab to be poured. Just as we had with phase one, this required areas between the foundation concrete to be filled with soil and compressed. Then stone was added and compressed again. A damp proof membrane was then laid, before Insulation Panels across the floor and finally reinforcement sheet metal laid in readiness for pouring concrete which happened on November 3rd. 

Sunset House progress

After so much preparation work, it is amazing how fast the final process can happen. The big cement pumping machine sets up and soon enough, one cement truck after another come to off-load and we see the cement slab being levelled into place. It’s exciting to see, but equally quite a realisation that all that work for months around foundations, levelling, reinforcement, damp proofing and so much more – is now covered and will never be seen again!

Sunset House progress
And how amazing it looks from the air, thanks to our Drone and Cameraman, Adi!
Sunset house by air!
This picture was taken November 4th when the Phase Two Slab was completed and set.

While the Slab was allowed to go hard, attention was turned to Phase One and the tremendous detail required for reinforcement and cementing of all the support columns and the endless number of Lintel Beams required over doors and windows. This was a huge time-consuming job, which seemed to go on forever! But as weather permitted, the crew pressed on and soon enough, the cements trucks were back, filling the columns and frames for the lintels.
Sunset House progress

At this stage, certain features of the building start being more evident, such as the elevator shaft and stairs around it, which is more apparent in this photograph.
Sunset house - elevator shaft
As the detailed but critically important work continued on phase one, further preparation work was being done on phase two. Most noticeable were the metal reinforcements for the support columns. All created by hand but set up ready for the walls to be built and tied into the columns, just perfectly.
Sunset House slab

On Monday, November 28th, in a meeting with the Construction company, we were informed of another increase in the cost of Bricks announced for January. Not wanting to increase the budget more than we needed to, we agreed to purchase the total bricks required for the entire building. Buying them now for use well into next year, would save a lot of money, so we agreed another step of faith to buy all the Bricks required and sure enough, trucks full of bricks started arriving the next day! Slowly but surely, we are running out of parking space, as more and more space is taken up with building materials!

Building supplies
It’s all go here in Cihei and very exciting to see the progress being made on this incredible project, we call ‘Sunset House’. The tremendous support received this past month is helping us to make significant progress. Support through donations and loans is enabling us to make decisions such as buying all the bricks now, which requires a lot of capital, but will save money without doubt later in the construction process.

Same as with the Hydrotherapy Pool, which we don’t need until May 2023, but to secure a good price and have the price ‘fixed’ we had to sign the contract this month and pay 50% deposit. At some point we will face similar issues with even more expensive equipment, such as the Sensory Room, but I think that can wait until the new year and then we’ll start looking at the detail required for our exceptional facilities being included in this wonderful project.

As I conclude this report, November 30th – the site is as busy as ever! We have a big crew of men working on many aspects of the building. We have the Cement Pump here and currently the third truck of cement providing more fill for support columns, lintel frames and the elevator shaft frame.

Sunset House progress

Sunset House progress

With so much activity on site, we need to ensure there is as much activity in raising funds to support the project. With just over £1million ($1.2million) totally paid by Christmas since we started in April this year, we will have a short breather until the next interim payment is due January 31st, 2023. That will be the start of another £1million ($1.2million) due by June 2023.
The pace of work is inevitably incurring huge costs, as we expected when accepting the major Construction to be done in 13 months, rather than the originally planned 36 months.

We must continue to do everything we can to meet our obligations on the construction and essential associated materials to enable the contractor to fulfil his part of the contract by May 2023. It is very exciting to hear from the Smiles Family of plans being made to support the project financially, but we need more to join the Visionaries and Enthusiasts to see these obligations met in full.

Please contact me at the e-mail address below, if I can answer any questions or help with any plans you have for partnering with us in the building of Sunset House, Cihei.

Sunset House aerial shot, November 30th
I leave you with this aerial shot taken late morning on November 30th, here in Cihei Romania.

Thank you for joining us to make this dream a reality.

Sunset House Donate $Sunset House Donate £

Kevin D. Hoy
Founder and Chief Executive
The Smiles Foundation

kevin@thesmilesfoundation.org


Link to previous Sunset House Reports

Email Newsletters with VerticalResponse