Sunset House, Cihei: Update & Gallery, December 1st, 2023
With the delays we have experienced in Construction, I was getting increasingly concerned as we got closer to winter arriving, how the bad weather could impact our schedule of getting urgent work completed so the next stage could get started! Well, earlier than perhaps expected, winter arrived, with the first reasonably heavy snow fall on Monday, November 27th!
The Internal gardens that looked so beautiful in the summer suddenly took on a different beauty when covered in snow!
Fortunately, while the snow was falling, exterior workmen could refocus on interior work, of which there was plenty to do, as a result of events during November, and I will go through these issues for your better understanding in this update.
As many of you will know, from reading the updates month by month, November was when we were hoping to see the Linoleum Flooring start being laid throughout the facility.
Having originally planned for this to be in September, delays in construction meant revising the timetable of several jobs, including the Floor laying, so in the summer it was delayed until October, and then, as weeks passed, November! I was seriously hoping to see the job completed by Christmas, allowing subsequent important work to be scheduled early in the new year.
As time passed, we became increasingly concerned that timetables were not being met and Derek Brothers offered to come out again and assess the building, as he had done originally in May this year.
We arranged for Derek to come November 13th to make his assessment.
In conjunction with the concerns over construction delays due to various complications, I had the opportunity to appoint on a short-term contract, a Construction Engineer who specialises in Project Management, Frank Fira.
We had worked with Frank 20 years ago during the building of the Tileagd Complex. He was a young, newly qualified engineer then, now he had gone on to become a successful and well respected engineer, working on many signifiacnt projects in major cities around Romania. Frank had just completed a contract at the end of October and was awaiting a new contract to start in the New Year. We discussed some of the issues with Sunset House, and Frank agreed to assist us at this critical time, esepcially while Maria and I are busy with Mission teams and SOS leading up to Christmas.
Frank’s first day was November 13th so was present to discuss and hear Derek’s conclusions on Sunset House building.
It didn’t take long for Derek, with Damp Meter in hand, and a walk around the facility, to conclude the building was a long way off being able to confidently lay flooring without risking problems, with it lifting off a damp floor within a few weeks of laying!
Alarm bells started ringing!!
We discussed what was needed and the main issue as you could no doubt imagine, was heat! The cold and damp of the fast approaching winter, needed heat in the building to combat the problems created by a cold damp atmosphere.
But, when would we have heating?
The Heat Pumps were on a Boat from China (is it the Slow Boat, I asked) and we were told they were due to arrive December 13th/14th. If all the preparation work was ready, the Heat Pumps could be installed and operational within about 7 days.
Before Christmas, I asked? Probably, if the Heat Pumps arrived on time!
To have Heating fully operational, we needed Electricity and Water connected to the new building and fully working. Electricity needed an approved Contractor to connect the building to our Transformer, already installed. The Generator we required as per ‘Approval Conditions’ was purchased in the United Kingdom and was planning to have come on the truck with Derek Brothers long before now. With him being delayed for Flooring, the Generator was still in Northern Ireland and not getting here until Derek came.
When was that now scheduled?
Discussions between all relevant parties – Smiles which included Derek and Frank, along with Maria and myself, were joined by Architect, Mara Vida and Contractor, David Cun – to take a hard realistic look at what needed to happen for the critical timetable to get ‘back on course’.
What was that critical time-table?
As you might imagine, for such a large building, providing Residential Care for so many people, the Authorisation Process to ultimately Function, is a complex and somewhat time consuming process. But the consequences of missing important deadlines, could cost Smiles dearly, such as lost Government Subsidies for 2025 of £125,000/$144,000 if everything in the process was not finished by very specific deadlines in 2024. If we missed 2024, the next application could not be until September 2025, for the 2026 year!
Certain issues are required for the first and most important approval – Construction. This ensures the building meets all the requirements stipulated in the Architectural and Engineers submissions at the beginning of the project, for us, that was back in early 2022. Everything must be approved and signed off for us to be given ‘Approval in Construction’.
For this we have to ensure Water and Electricity is connected. Safety Railings on the Roof and Balconies are installed. Fire Department requirements are all met, both interior installations plus Pump House and Water Reservoir outside. The Generator needs to be in place and operational.
So – calendars were out and specific deadline dates were discussed, and this is what was concluded.
- Heat Pumps installed and working by December 22nd, 2023
- All Safety Railings to Roof and Balconies to be fully installed by January 19th, 2024
- ALL interior Work by the Main Contractor would be finished by January 19th, 2024
- Derek Brothers and team arrive for Floor Laying to start January 22nd, 2024
- Electricity and Generator to be fully connected and opertional by January 31st, 2024
- Water Supply to be fully connected to the Building by January 31st, 2024
- Fire Department Requirements completed and approved by January 31st, 2024
- With above finished, CONSTRUCTION INSPECTION arranged and approved by February 26th, 2024
- Once Construction approved, Topograph enters Project in Land Registry by March 29th, 2024
- Once Land Registry Document available, Approval to Function, can be obtained by April 30th, 2024
- Once Approval to Function is obtained, Staff and Residents can start to move in from May 2024.
After 3-months of Functioning, we are assessed and approved (hopefully) for the License to Operate a Residential Facility. This would be avilable to us by end of August, 2024 allowing us to apply for the 2025 Subsidies by the Application deadline of September 30th and if approved, Subsidies would be paid from January 2025.
I’m sure you can see and appreciate the pressure we are under to meet these deadlines and that pressure will continue, to ensure each section of work is completed and each approval is dealt with, in the offical time allowed by law, on average 30-days for each Official Department.
This will all take considerable attention to the project and detail of each part, as one area slipping can impact the whole strategy and that can prove very expensive, especially when we are committing to extra expense now, to help meet the deadlines and achieve the objectives.
So, what are we having to do, to ensure we meet these goals?
The Heating and Plumbing Engineers are working every day to be prepared for the arrival and installation of the Heat Pumps. Now potentially 12 days away as of December 1st!
Concerns about Water Supply following close consideration of issues this past summer, when for the first time ever, our second Well in Cihei, installed in 2004 for the Mission Centre, ran low on water. A hotter and dryer summer put the pressure on our water supply, and so we were faced with drilling another well to ensure the significant amount of water needed for Sunset House, would be available, whilst maintaining supply to the other buildings on the Cihei site.
To cut a long story short, it was decided in November to drill a third well at the north end of Sunset House which has now been done, and a good supply of water was hit at 100 metre (300 foot) depth. This was extra to our original budget, and is expected to cost up to £18,000/$21,600.
Exterior Tiling of Balconies and Patios were hoping to be done by Volunteers on Construction Specials next spring. The need to have Safety Fencing installed by mid-January, meant Tiling for exterior areas needed completing before Christmas!
We had also hit a problem with our plans to use Bathroom Cladding in the Residential Wet Rooms. Discussions with experts here informed us ‘Cladding’ was not a generally available material in Romania, and even if accessed outside and brought in, no one knew of experienced fitters who could install it.
I therefore had to suddenly revert to the idea of Tiling, rather than Cladding. Derek said, where as Cladding was to go over the linoleum to ensure waterproofing, if tiles were used, better to have them in before the flooring and he would lay the flooring accordingly. It felt like so many issues were changing and needed urgent attention at a difficult time of year and putting the budget under immense pressure months ahead of schedule. However, if the deadlines were to be met, we needed to see what could be done to ensure the smoothest of schedules through all the processes.
I rapidly started exploring options to find a contractor at such short notice to do some 930 sq metre (10,000 sq ft) of exterior tiling in Wintery conditions and Interior Wet Rooms – all 31 of them!!! After a few options were considered, we agreed the best contract with the current Finishers who were working on the Exterior Insulation and Render. They could bring both, extra men, but also alternate between exterior and interior as weather conditions allowed.
We contracted directly with them on November 17th having to then source and purchase, all the additional Tiles and Adhesive, which cost £8,400/$10,000.
We also had to face a considerable cost in labour, which is now contracted at £15,000/$18,000 and to be paid by weekly installments from November 24th until December 22nd when we trust they will be finished. We had already purchased the Patio and Balcony Tiles in the summer, so they were ready and waiting for installation as weather permitted.

With a plan in place for Tiling to be finished by Christmas, we then had to bring forward payment of the Safety Fencing which needs to be installed by January 19th, so on November 22nd, we paid £41,865/$50,238 to ensure that aspect could be met. It was going to take a month for the Fencing to be manufactured and payment was required upfront for such a substantial order.
For the Safety Fencing to be installed on the Roof, metal capping needed to be fixed and thankfully that was started and is now almost finished around the entire Roof perimeter and rooftop Gardens.
All in all, it has been a challenging, stressful and demanding month. With additional costs of £83,265/$100,000 agreed, we are now, most certainly, in the total FAITH hemisphere.
I have taken this opportunity to explain in considerable detail the issues we have faced this past month alone. I know this is a big project, the biggest we have ever taken on. I knew it would come with many challenges and the project hasn’t let me down!
I also knew this was God’s Plan for the next chapter in Smiles, and accepting it wouldn’t be easy, I know God is on our side and the Smiles Family are amazing, so I trust now, by end of year, or even in January, many will be able to help us meet these expenses, both those unbudgeted and those needing to be paid much earlier than expected.
In Faith, I thank you for your tremendous support and look forward to sharing an update on progress with more pictures and hopefully less words when I prepare the New Year/January report on Sunset House.
My sincere thanks for your continued interest and support for this incredible project. Please continue praying for and supporting Sunset House, by every means you can. Thank you.
Kevin D. Hoy
Founder and Chief Executive