Sunset House, Cihei: Update & Gallery, February 1st, 2023
For some, getting started again after Christmas and New Year, is slower than for others. This was my feeling with the work force on Sunset House, Cihei.
Many of them live far away, and therefore planned an extended Christmas break, knowing once they were back on site, it might be several weeks, if not months, before they would be home again. By January 16th, we had workmen and the crew started to grow day by day. By 23rd, it was all systems go!
Allowing for those extended holidays and some winter weather days, inevitably work slowed down. Watching from the office every day can make that a tad frustrating, but I am also mindful how tough it must be on the crew, doing their work in such cold temperatures. Currently working every day at tempertaures, bearly above freezing. 3/4C (37-39F) being daytime high. I even saw them working through a snow storm this past week! Fortunately, the mild blizzard only lasted a couple of hours!!
Although we only enjoyed a couple of weeks of full output in January, we certanly saw progress with many men on site. Metal Work progressed very well for the support of Walls on Phase One, upper level. We should see blockwork started there imminently as the metal structure for tying in the brick walls was finished by January 28th.
Phase Two had a lot of woodwork being done to provide the shuttering around support pillars in preparation for more cement pouring, which will happen very soon, subject to weather. It might even happen by 31st, and if it does, I’ll be sure to include a picture. If not, next month …promise!

Then Shuttering preparations for pouring cement to the Support Columns of Phase Two.
If the weather is kind during February, we will see all the walls for the upper level on phase one finished and hopefully the upper level slab of Phase Two. These two achievements will make the building look tremendously progressed and in my heart of hearts, I’d love to see it before I leave for America, but that maybe asking too much for all to be done in 3 weeks!
We will for sure, during February, see the Electricians on site for the first fix of wiring in Phase One and not too far behind them will be the Plumbers doing their first fix for the 40 bathrooms that are in the facility, plus water to the medical rooms, including Hydrotherapy Pool and then of course, the Kitchen. The List is long, but with 106 rooms – these professional tradesmen have a lot to do and will be around here for a few weeks, for sure.
It was great to have our Architect visit the site this past week, taking a very careful interest in the work, its progress, its standard of completion, and always checking it is done precisely as her Drawings require!
That’s important, because the State Inspectors will compare the finished job to the Approved Drawings and will expect all the requirements to have been respected. I am very confident with the Team involved in overseeing the project, more so than on any previous Construction Project, Smiles has undertaken.
As you might imagine, there are endless issues to plan and research for once the main construction is finished and we move to the interior finishing and eventually exterior with roads, gardens and landscaping.
Whilst all the construction continues, I have also been blessed by some meetings on those ‘future’ issues. For example and for your continued prayers, I met with the owner of a specialist flooring company in January who expressed desire to assist us with the specially approved Medical Vinyl used these days in such facilities. Hospitals, Clinics, even Schools now use this safe, nonslip, hygienic alternative for floors and wet rooms.
We anticipated a budget of at least £75,000/$93,750 for the entire Sunset House requirements. The specialist company I met are now looking at what best price they can secure the material for and then see if their specialist team of fitters, can come to Romania and get the job done without charge for the work. This could potentially halve the cost!
Similarly, but different, I was at my hairdresser last weekend, and as you do, you chat away while they cut about a multitude of things. Be honest, you do talk about so many different things! Well, as you might imagine, I talk about Smiles and particularly the Sunset House project. By the end of my session, about 35 minutes, I had the lady agreeing to come to Sunset House once opened, offering her professional services with hair, for our residents, for free!
I am encouraged by the number of people who want to serve the Lord, and they just need opportunity and encouragement. I believe my hairdresser will be blessed and so will the residents who I know look forward to looking right, with hair and all done. Now I’m looking for a manicurist and pedicurist who can get involved with our Ministry at Sunset House when it opens next year!
This is why I launched the Construction Special Trips in January. I believe many skilled and unskilled hard-working people would love to share their service hours helping prepare Sunset House for Opening. Labours of Love, most certainly, but that’s what Sunset House is all about. LOVE – shown to those who have served well through their life and whether elderly, disabled or vulnerable – need our Love which comes from God to assure them they are truly loved and appreciated every day of their life.
So, don’t forget, May 27th, 2023 we begin our Construction Specials – encouraging skilled and unskilled supporters to join us to tackle the extensive list of tasks which we anticipate could be a 12 month process. Please see the Special Construction Trip options to see if you can help.
The Smiles Foundation » Construction Plans for 2023
For us to be ready for the Volunteers starting to arrive in May, we need to see the project completed as planned back in April 2022, when we cut the Construction time from 3 years to 13 months. God Willing, this means the main Construction will be finished by June 2023.
To achieve this we must pray and act towards the Financial Commitments needed for our obligations to be met. Which are currently:
£250,000 ($312,500) by February 28th, 2023 We currently have £127,273/$159,091 towards it.
£450,000 ($565,500) by March 31st, 2023 We currently have £200,000/$250,000 pledged.
£250,000 ($312,500) final main Construction Payment to complete the Contract in June 2023.
Please pray and consider how you can help with this God-Sized miracle becoming reality – all for the Glory of God, here in Romania. Donation, Grant or Loan is all helpful, appreciated and signifiicant, whatever the amount might be. As is often said …. Every little helps!
If I can answer any questions for you, please just contact me by e-mail or a message to the Smiles Office. I’ll get back to you as quickly as I can.

So, the sun sets on another month of exciting work and opportunity for Sunset House, Cihei.
I look forward to sharing more updates with you next month.
My sincere thanks for your interest and support in this incredible project.
Kevin D. Hoy