Sunset House, Cihei - Update

Sunset House, Cihei

Sunset House, Cihei: Update & Gallery, February 2024

Sunset House Donate $Sunset House Donate £

As we work through these exciting days, we realise the target date is getting closer. Actually, as of today, we have 255 days before the Grand Official Opening of Sunset House, Cihei.

That may be the main reason we feel the pressure on every aspect of this project, as we work to meet time deadlines but also face the budgetary demands of these finishing aspects of Construction, but then the huge challenge of furnishing the entire facility. When you start ordering the quantities of equipment needed, furniture needed and even linens such as Bedding and Curtains, one realises all too well, the size of the place and the number of people that will be cared for in Sunset House.

One crucially important aspect we reached in January was the finishing of exterior plastering and rendering. Now the entire facility is finished and protected as planned.

There were still more issues requiring attention and those that were possible to do in the winterery weather, have been done, which is great news. Further sealing of the Roof was important to stop those final little leaks dripping through. We sincerely pray that has now been resolved, which recent dry weather helped us tackle. But now, until we get some strong wind and rain, we won’t know for absolute certain, but we most sincerely pray, after the next heavy rain, all will be dry and well.

Being totally dry inside the building was an essential requirement before we could have Flooring installed which we had hoped to see started in January. That proved impossible due to dryness, so further discussion and assessment was had and now we are working to be ready for Flooring in the first 2 weeks of March. By this time next month, we will have a date for starting, I’m sure!

Part of the Drying process also involved the Internal Gardens. They also needed ‘Sealing’ to prevent dampness penetrating the concrete walls and floors into the Building.

This week, a specialist team have started the Work, making the most of this dry, milder weather we are enjoying in Romania.

Sunset House - Sealing

Further exterior work involved Safety Railings to be installed on all the Room Balconies but also on the Roof. And both have been completed during January, with some final bits done even today!

Sunset House - Safety Railings

Along with many of the planned works being completed, we also had some surprises of work or equipment that was now necessary, that wasn’t expected or budgeted for. We have already faced some such issues, such as needing to drill an additional Well for guaranteed water supply given the volume of water Sunset House will use. This added £17,000 ($21,250) to the budget.

Then switching Bathroom Cladding to Ceremic Tiles and bringing forward the work 5 months, meaning Contractors were hired in Romania, rather than Volunteers doing the work in April.

The work is all done, but at an additional cost of £23,000 ($28,750).

Now we have another item, having been assured our current Electricty Transformer was adequate for the new facility, we have discovered it isn’t! When we turned on the Under-Floot Heating in December, it tripped the master power supply. After investigations and professional assessment – a New Transformer was required at a cost of £10,000 ($12,500)

So, the Old will soon be gone ………….             …… and a New will be installed.
Electricity Transformer

Such issues are adding great burden to these final months of construction and finishing. But we trust the Lord for provision and know the Smiles Family are fully behind the Project and will do all they can to help us through to completion, as planned and not have to start considering limitations on what we can do due to lack of resources.

Where we can, we are pressing ahead at full speed. So many aspects of the project need considerable advance notice to get sufficient supplies for the large orders Sunset House involves.

Bathroom furniture will soon need ordering involving 42 complete Toilet and Sink units, plus 35 Shower units. Anticipated cost based on quotations received would be £11,500 ($14,375).

Sunset House - WardrobeSunset House - WardrobeThen Wardrobes – fitted for each Residential Room. We had one ‘trial unit’ made at a cost of £900 ($1,125) but when finished we really didn’t feel happy with it and hesitated with ordering another 30! It won’t be wasted, as certainly a beautiful piece of furniture but for somewhere else, not each Residential Room.

So, another company came and built an alternative style which was a truly ‘fitted’ wardrobe. Everyone was happy, really preferring the new design and so an order was placed for 30 more. The cost is £21,700 ($27,125). A substantial amount, but £200 ($250) each less than the first option!!

Sunset House - Fitted Wardrobe

It pays to go the extra mile and check all your options, even when there are so many things to do.
And so the work, issues and challenges continue. I know we will encounter many more over the coming months before we can truly say, Sunset House is finished.

To help us ‘finish’ we need your help.
The plans for 2024 are critically important in terms of Timing and we need a lot of help to see all the objectives achieved. Can you help? Or do you know people who could help? Tell them of this amazing opportunity and get a few to come and get ‘stuck-in’ with getting these jobs done.

From March 16th, the list of finishing work is daunting, but with many hands put to the plough, I have no doubt we can do it. With God’s Help and Strength – Nothing is Impossible.

PLUMBERS – ELECTRICIANS – PAINTERS – LANDSCAPERS – WILLING HANDS
If you can consider helping for a week or more on a Construction Special Mission Trip, during March, April or May, let me know which area of work you could help with, and we’ll schedule you into the master plan of finishing Sunset House, Cihei.

For early January, I put together a short Video to summarise the needs and hopes for the process of finishing Sunset House. I encourage you to take a look, if you haven’t seen it and share it with friends and family to see who can help with what, so that this God-Sized project can get done.

Do contact me anytime by e-mail or through the Smiles Office to see how you can be involved through Prayer, Financial & Practical Support.

The 5 minute Video – YouTube link:
Thank you for your continued interest and support for this incredible project. Please continue praying for and supporting Sunset House, by every means you can. Thank you.

Sunset House Donate $Sunset House Donate £

Kevin D. Hoy
Founder and Chief Executive
The Smiles Foundation

kevin@thesmilesfoundation.org


Link to previous Sunset House Reports

Email Newsletters with VerticalResponse