Sunset House - January 2024 Update

Sunset House, Cihei: Update & Gallery, January 2024

Sunset House Donate $Sunset House Donate £

A ‘Happy New Year’ has already been said many times, but I confess to wondering, how good will the New Year be for Sunset House, Cihei and our extreme efforts to build a first class Residential Facility that will bring Glory to God and share His Love with so many in the years to come, those who are Elderly, Disabled or Vulnerable. For sure, my prayer was for a Happy New Year with more miracles unfolding before our eyes as we continue this great challenge into its third year!

In December, I detailed the revised ‘Calendar’ we had agreed with Constructor, Architect and Engineers which included: Heat Pumps installed and working by December 22nd, 2023.

This was number one on the list, as getting heat into the Building was essential to begin preparation for Derek Brothers to come in January to lay the Linoleum Flooring throughout the building. The Heat Pumps were coming from China, by Boat, and were scheduled to arrive December 13th/14th but as we prepared to finish for the Christmas break on December 22nd, the Heat Pumps had not arrived!

Feeling somewhat devasted that all our efforts seemed to be missing the mark, I called an urgent Management Meeting for Smiles Executive, attended also by Frank Fira to discuss the implications. That was December 18th, knowing the Heat Pumps had not arrived on time and therefore needing to consider what options we had for moving forward trying to meet the rest of the new Calendar deadlines.

In many ways, it was a potentially depressing meeting as we reflected on the numerous delays faced since the early days of the Construction process, that never seemed to be caught up on. Just as some progress was made with past problems, new challenges seemed to be forever raising their head. I had a true sense of the Devil meddling with the whole process, endeavouring to complicate and derail the plans God had given us for this project.

With a commitment from all involved we would not allow that to happen, Plan B (or was it C or D) had to be put in place!

In consultation with the Heating Engineers, it was proposed to consider using Hot Water Tanks (Emmersion Heaters basically) to provide the hot water needed throughout the Underfloor Heating system, to dry the place and prepare the floor for linoleum.

Additional cost factors to consider was Distilled Water for the entire system (About 8,000 litres/2,285 US Gallons) and due to starting the system in winter, they recommended Anti-Freeze in the system, in case any problem arose with the electricity, prior to the Generator being installed which could then cause a freezing and bursting of our entire underfloor system!!

Quite a risk, but £3,567/$4,458 was a price we decided to pay to take away the risk of freezing, so the Engineers agreed to work between Christmas and New Year and during December 27th, 28th & 29th, the job was done and Praise God, we had heat coming through the floor before the end of the Year. They will be back on January 3rd to continue the process for the system upstairs to be connected and heated by January 5th.
Linking up heating

Hopefully, that ‘slow boat’ from China will come in soon and the proper Heat Pumps will be installed, but meanwhile an answer to prayer, was having Heat.

(Update) – Ship arrived Constanta (Romania) on January 2nd – so now it is clearing Customs and the Heat Pumps will begin their journey to Cihei.

Another crucially important job to be completed was the final ‘sealing’ of the Roof as in early December, we were still experiencing some small leaks into the building, which of course had to be stopped, but especially before the Floor would dry out for laying Linoleum.

Sunset House Roof sealingFinally, just before the Christmas break, sealing the roof was also complete, at least according to the Contractor. Of course, as we often say, ‘proof of the pudding is in the eating’ so basically we had to wait for rain, and some heavy rain, to see if the Roof was truly ‘Sealed’.

Dry inside Sunset House!We have had quite a bit of rain over Christmas and anticipate more during early January, but the fact is, currently, we have no leaks in the Building, so yet another prayer is being answered.

All is looking good for Linoleum to be fitted in January!

As we started to plan for various Inspections that would be required on the Building to meet aspects of our new Calendar Deadlines – we had to address the Fire Department requirements which included an Underground Pump House to be built, which in winter was to prove a very messy job!

It started with a rather large hole being dug, followed by metal reinforcement, shuttering and then a lot of concrete!
Preparation for the pumphouse

But as planned, the Pump House was completed and on December 28th, Pumping Equipment was installed and connected to Electricity and the new Water Well.
Pump house

Another major task that was recently decided to be undertaken much earlier than originally planned, was tiling. Tiling on Balconies, Patios and Bathrooms.

All made some tremendous progress in December and we anticipate having it all finished by January 20th, when the floor linoleum installation will hopefully start.
Tiling

With the New Water Well functioning, Electricity connected from the main Transformer to the Building, Heat coming through the Floor, and even Grid Ceilings starting to be fitted, it felt we were ending the Year on some very positive notes.

With our thoughts firmly fixed on the Calendar Dates we set for 2024, we continue to pray all the varying issues will come together, somewhat against all the odds, but completely in line with God’s Plan, for Sunset House Cihei. The plans for 2024 are critically important in terms of Timing and we need a lot of help to see all the objectives achieved. Can you help? Or do you know people who could help? Tell them of this amazing opportunity and get a few to come and get ‘stuck-in’ with getting these jobs done.

From March 16th, the list of finishing work is daunting, but with many hands put to the plough, I have no doubt we can do it. With God’s Help and Strength – Nothing is Impossible.

  • PLUMBERS – There will be 35 bathrooms to furnish – installing Toilets, Showers and Basins.
  • ELECTRICIANS – There will be electrical 2nd fixes to complete, including lots of Lights throughout the building.
  • PAINTERS – There will be a final coat of paint to apply throughout the facility, leaving it fresh and clean after all the work.
  • LANDSCAPERS – In April, the Outdoor work starts in earnest, with a large Decking Area to be built beyond the North Lounge, which Trustee, Ian Steenson is taking responsibility for, but I’m sure he would welcome some help in the process. We will need landscapers, gardeners and several workers to see the Grounds of Sunset House prepared and not least, to install the Patio Roof Gardens, which will be something very special indeed.
  • WILLING HANDS – If you can consider helping for a week or more on a Construction Special Mission Trip, during March, April or May, let me know for which area of work you could help with, and we’ll schedule you into the master plan of finishing Sunset House, Cihei.

Plan to come and be a part of something very special!

As we enter 2024 and face the finish of this incredible marathon project, I prepared a video to show further progress to date and a reminder of our plans ahead in the New Year. Enjoy the viewing and consider sharing it with friends and family, so we can get as many people involved as possible through Prayer, Financial & Practical Support.  It’s as simple as sharing this LINK.

Thank you for your continued interest and support for this incredible project. Please continue praying for and supporting Sunset House, by every means you can. Thank you.

Sunset House Donate $Sunset House Donate £

Kevin D. Hoy
Founder and Chief Executive
The Smiles Foundation

kevin@thesmilesfoundation.org


Link to previous Sunset House Reports

Email Newsletters with VerticalResponse