June has been the start of a very busy, but critically important 3 months for Sunset House and the Team involved with overseeing its construction.

The original plan was for the Main Construction to have been finished May 31st, 2023 – but unfortunately, various delays were experienced during construction and a revised assessment was made, that the main construction would now be completed in September. A 3-month delay which started June 1st and is now on a ‘countdown’ to completion.

For sure, the intensity of the schedule can now be felt by everyone on site and in the office, as having geared ourselves towards the original demand of a 13-month construction period, many arrangements were organised around that schedule, so now it is important the adjustments made for the 3-month extension are adhered to, and no further delays are encountered.

With the Phase One Concrete Roof Slab poured at the end of May, we soon started further shuttering for safety walls around the Roof Top Gardens and the entire Roof Perimeter. I had the opporutnity of climbing up to the top (Don’t mention it to my insurance company!) but what an amazing view.
The finest in Cihei I’m sure, with spectaular views North, South, East and of course, the Sun Setting West! From the Roof, you can experience the Sun Rise and the Sun Set – making this location, the place to be. Don’t leave it too long before you see it for yourself.
Sunset House Roof

Inside the building, work needed to start on time critical aspects such as finishing the Plastering with the top layer skim that would be the finish for painting when the first Construction Special team arrived June 17th.

So, the Plasterers got to work….
Plasterers
…. And by June 16th, twelve (12) residential rooms on the lower level of Phase One, were ready to Paint.

The Construction Special Mission Trips, introduced this year to specifically help with primarily Sunset House, but could also be doing important work on any Smiles project, kicked off on June 17th and nine people came from Scotland, Wales and Northern Ireland to get us started.
What an amazing job they all did! While Electricians and Painters worked hard at Sunset House, others took on challenges at Etol’s House in Mierlau and then fantastic work at JFL, Salonta.
Electrics

Installing Socket and Switch Units, six in each room of the 12 rooms that were ready, presented a challenge, but by the end of their week, all 72 units were very professionally installed.

Working around the Electricians, while also keeping the place very clean and tidy, four ladies undertook the painting process. 12 bedrooms and 12 bathrooms all needed Ceilings to have up to 3 coats of paint each. By the end of their week, 72 coats of paint had been applied, and the ceilings looked so nice, our electricians fitted 12 central light units for good measure!
Ceiling work

Clearly, some of these finishing touches were making the facility very welcoming and during the month we had our first residents arrive, rather unexpectedly, but never the less, very beautiful.
First residents
The only problem I now have, with the birds nesting to raise their young, we can’t move the nest until the family move on, so suspended ceilings in the corridor are going to wait a little longer!!

The month was very busy with Deliveries, some we hadn’t truly planned for, at least not in June!
One huge delivery that was planned was the Elevator, which arrived early in the month from Spain where it was manufactured, but due to delays with the building, we had to store it until ready for installation. Twenty-nine boxes of material were delivered and some very heavy metal frames. Thankfully, our American Team from NE Tennessee had just arrived, so they helped us carry some of that heavy stuff into our Store Room. The elevator shaft is being worked on, and we expect Installation to begin early August.
Elevator

Kevin's ShirtLiterally while the Elevator was being unloaded into the Store, the first Windows arrived for installation. ‘Never rains but it pours’, and it so happened that morning, it was pouring with rain!

Here is my shirt after I came in from supervising the unloading of the Elevator. It really did rain!!

But, after a change of shirt, I was back out on site to instruct the window installation team, where they were to start.

With Maria out on the field with a Mission team, I turned to Nina to assist with translation, to ensure the windows were fitted in the correct place!
Window deliveryAs I said, some deliveries were not so planned in advance.

As often happens with me, I woke up in the middle of the night thinking about a major logistical challenge that we needed to act on fast. It related to the Internal Gardens. We have five of them in the facility and we had been discussing during the day, the scheduling of Installation for them.
I woke up in the night thinking, how will we get a 5 metre (15 foot) tree into each garden once the frames are installed, as then we would only have a regular door to access inside the garden.
Next morning, I shared the thought and sure enough, if the tall trees were not in place before the frames were built, the ony realistic way of getting them in was by crane from the roof! That could be tricky, and very expensive!! So, Maria and I headed to the Tree Nursery and sure enough, purchased three 5 metre trees and three 3 metre (9 foot) trees so that each of the first three Interior Gardens had the tall mature trees in. This was all done last week and this week, the Garden Glass Frames were installed.
Trees

I must say, the Internal gardens already look amazing and there are only 2 trees in them. Wait until the small plants and flowers are added next year. I think we could have several more birds taking up residence!
Internal garden

Back outside, plenty of work was taking place. For much of the month, external plumbing was undertaken. The JCB was in digging deep trenches everywhere for endless pipes, especially for the rain water that will fall from such an enormous roof. It was a lot of mess while the job was being done, but all was completed with all the pipes covered by June 30th. Right on Schedule.

Digging trenches

PipeworkWaiting for the Plumbers to finish and have all the soil back in place, were the external finishers who started this last week of June, with Insulation of the building exterior.

Another huge job for this massive facility, but great to start seeing the building blocks, that have been visable for more than a year now, slowing being covered and soon, like so much of the Sunset House Construction, will never be seen again!

Once those blocks are covered with insulation, they will be skim plastered and then painted.

This building is going to look amazing.

That pretty much covers the entire month and brings you up to literally the last day of June.
Sunset House exterior

I have focused on so much of the interior work, that in closing, I should mention, the entire time all this work was happening inside and out, the main construction team were working on the shuttering of the Phase Two Roof. Next week, the metal reinforcement work begins and by July 12th, we are scheduled to see the cement poured on the Phase Two roof. At which point, the entire building will be finally covered, allowing important work to start below the roof with Electrics, Plumbing, Under-Floor Heating, Plastering and so much more.
Support and shuttering

Support and Shuttering for Roof of Phase Two in preparation for the Cement Pouring July 12th.
There will be so much again to report next month, I really am so excited, I can’t wait – but meanwhile, every day, so much is happening, that we give thanks daily to God for His Wonders in enabling this magnificent building to be constructed to His Glory and for the Blessing of so many people, here in Romania.

My sincere thanks for your continued interest and support for this incredible project. Please continue praying for and supporting Sunset House, by every means you can. Thank you.
Sunset House Donate $Sunset House Donate £

Kevin D. Hoy