Sunset House, Cihei: Update & Gallery, June 1st, 2023
The month of May has been an exciting, yet challenging, month on the Sunset House Project. But with the inevitable stress of such a project put to one side, I feel tremendous progress has been made and now I can truly see the final plans falling into place on the main structure of this building. For those who have been able to see the progress on site, I see and hear from talking to them, a real excitment for what they are beginning to see develop from an Architectural Design to a living reality.
Sometimes those Architectural impressions are hard to visualise in reality, but with Sunset House, we are now seeing just how accurate the impressions were and just how amazing the final facility will be!
As I mentioned in the report last month, several aspects of the building were being worked on and at times it was quite chaotic on site with several teams working on their expertise within the construction. All of that is now evident in the progress being made. With some aspects, rather like with the foundations, a lot of the work other than being here at the time, will rely on photographs to show what was done, as much of it will be covered and never seen again!
This is the case with several important tasks that progressed this past month.
The huge task of Underfloor Heating, with thousands of feet of heating pipes laid over every inch of floor.
That is then completely covered with levelling concrete which is providing the basis for the clinical linoleum to be laid in a few months.
When I see the thickness of the cement on top of the pipes, I wonder how the heat will get through to the room, but I’m assured by the experts, it will! And I sure hope so, as there are no radiator back-ups in any of the residential rooms!!
First Fix of Electrics and Plumbing is now complete through the entire facility.

As that was completed, so the Plasterers could follow on and now we see all the Ceilings and Walls having their first layer of plastering complete. A few rooms even have the top skim done.
The next major component is to see the start of fitting the 410 windows and doors. Obviously a lengthy process, but in line with our latest hope, the first windows will start to be installled on June 6th. This will allow plasterers to get in those rooms to finish plastering around the newly installed windows and then, with a secure sealed room, the final skim of plaster to ceilings and walls can begin.
The timing of this is important, as we need a week or so for the plaster to be completely dry before we start the painting process to firstly Prime (seal in the new plaster) before an undercoat and top coat of paint.
Trusting all plaster of designated rooms will be thoroughly dry by June 12th, the first layer of prime may be possible soon after, so by June 19th as scheduled, we will be ready for our first major Construction Special team to start work, which will involve lots of cleaning, painting and second fix of electrical components of light fittings, switches and outlet sockets.
Turning attention back to the exterior work, the Structural Columns being prepared last month have had concrete poured for the second phase upper floor.
At the same time, the construction team were continuing the huge task of support for the Roof on Phase One. This required the shuttering to be in place across the roof area, then completely boarded over before metal reinforcement was laid and finally, to my great joy – concrete was poured, as the roof section for phase One was done.

Whilst until now, phase two trailed phase one quite significantly, in recent weeks, the work schedule bridging the gap between the two phases has increased. If all continues to go well, within another 5 weeks or so, the Roof will be complete on phase two also, meaning the entire building is sealed and able to progress fully with interior work.
Having so many Mission Teams over the next few months, we anticipate plenty of help with the task of progressing the interior. The main work Teams will help with Cleaning and Painting which will feel like a never ending job on such a large facility!
We have electricians coming to help install (or at least begin to install) 392 light fittings throughout the 106 rooms. Plus of course 180 light switches and a further 349 outlet sockets!
With lots of hands coming for cleaning, painting and electrics throughout June, July and August – I do believe we will see great progress but we need to keep a close eye on every aspect of the schedule, planned and agreed to quite some detail!
In January this year I met Derek Brothers who owns a specialist flooring company in Moy, Northern Ireland. 4 months later, Derek came to Cihei, Romania to meet us on site at Sunset House and spend a long day discussing all the complex details of supply and fitting the entire facility with Clinically approved Hygiene Linoleum flooring. Derek needed to see for himself the task as he was considering, to what extent he could help us with our needs for Specialist Flooring.
He was in Romania less than 48 hours, but has returned home, agreeing to assist us with complete installation of the fitted linoleum that is likely to involve up to a month’s work for Derek and his team of experienced fitters. He will do this for us at the special ‘charitable rate’ of zero! Yes, amazingly, Derek has agreed to do all the labour for free. I cannot express how grateful we are for such generosity and pray the experience of being here at Smiles for the month will have a significant impact on each and every member of his team. 
We are anticipating the linoleum to be fitted during September/October. The exact time will be determined by the completion dates of the entire interior building and allowing for the concrete floors and plastered walls to be completely dry. Meanwhile, lots of samples to browse over and make decisions on style, colour and quality!
If all goes to plan, we will then need volunteer Plumbers to come as part of our Construction Specials from October onwards to fit our 33 Wetrooms, with Showers, Toilets and Basins plus several other facilities throughout the building. I’ll be hoping to see that complete by December, so if you have Plumbing Skills, please consider a trip and contact us to see the best time to come.
If we manage what we have planned by Christmas I’ll be delighted and thankful. It will certainly help me to have a more relaxed Christmas than it might otherwise be!
All this work involves a huge amount of money. Please continue to pray for us to be able to meet all the obligations coming up in the months ahead and do help wherever you can with a special gift for Sunset House.
By May 2023, we have managed to pay total Financial Commitments of £1,563,000 ($1,875,600) which is astonishing in a little over 12 months. For June, we have commitments coming due, totalling £280,800 ($337,000) so as these monthly needs get harder to make, I ask you to pray for God’s provision and please consider how you can help.
We have Flooring Material to purchase at around £45,000 / $54,000
We have the Elevator to pay for as its manufacture in Spain is now finished. £29,000 / $34,800
We have an advance for the Safety Fence to be paid. £31,200 / $37,440
And these are without the main monthly payments we are committed to make to the Construction Company as well as the Window/Door manufacturer.
Whether Donation, Fundraiser, Grant or a Loan – all is helpful, appreciated and significant, whatever the amount might be, it will enable us to maintain our payments to all contractors to ensure the schedule for each critically important stage of this building be met and respected by all concerned.
I appreciate that with such a large project, you could have questions that my general reports fail to cover.
If you have any questions for me on this very special project, please contact me by e-mail or a message to the Smiles Office. I’ll get back to you as quickly as I can.
Meanwhile, I sincerely trust you enjoy taking a visual recap on the past month’s work with the new Video we have produced on Progress at Sunset House.
My sincere thanks for your continued interest and support for this incredible project.

Kevin D. Hoy
Founder and Chief Executive
The Smiles Foundation