Sunset House, Cihei: Update & Gallery, June 2024
The excitment is growing for the Grand Official Opening of Sunset House. As of today, we have 133 days before the real Celebrations and Thanksgiving begins.
Inevitably, work on and around Sunset House is at an intense level now as pressure is on to put all the delays and frustrations behind us and focus on the many tasks requiring attention to reach the finish line.
As is quite often the case, as you undertake one job that you anticipated and budgeted to require certain time and finance, you discover other issues that need more of both before progressing! We have had a fair share of such surprises and disappointments – but that can’t hold us back. Each issue must be dealt with, and we trust God to provide the People, Skills and Resources to do as necessary. Sunset House is a truly beautiful facility, and I am striving in every way I can, to ensure the Finished Project is something that will bring Glory to God and that we can be proud of His Guidance and Provision each step of the way.
The last week of April saw some major tasks dealt with.
The Sensory Room was virtually completed and would have been finished if the Dutch Manufacturer had not made an error with an important item of equipment. As a result, John Montgomery responsible for the Sensory Room had to get a new piece made, shipped from Holland and plans to return in July to install it. We are thankful he can do that and hope the extra time here will allow some proper ‘training’ of our Residential Staff on how to use the Sensory Equipment for greatest impact and success.
We had a great Construction team here the end of April working on many aspects of the project. Ian Steenson and Tony Farquhar took the lead in jobs they knew nothing of when signing up to come! Thankfully, skilled people can adapt and get down to work very fast as circumstances demand. One major job we didn’t anticipate was the Retaining Wall needed around the Terrace Patio outside the North Lounge. A Large patio of 100 sq.metre/1,080 sq.ft
The guys worked so hard to get that built and they did it with some late nights and early mornings.
The week after they left, Maria had detailed instructions from them of how to fill the wall cavity with cement, and sure enough, even with some guidance by WhatsApp video – the cement was poured …
… which allowed great progress to be made during May with finishing the Terrace Patio.
And does it look good? I believe so.
The Terrace Patio was a large area, but not the largest. The same company were contracted to do our path around the entire building, including Entrance areas to the Main Doors, Mechanical Rooms, Dining Rooms and a Delivery Area to the Kitchen. A huge job with various ‘extras’ we were not aware of at the point of starting.
Although I am delighted with the finished results, the Budget virtually doubled, from £23,000/$28,750 to a finishing cost of closer to £40,000/$50,000. I suppose that’s why I had a contingency figure for the project from the very beginning, but at this stage of the project, around 70% of that contingency fund has been used, mainly in the early days when a considerable number of Materials increased significantly in price due to the Russian invasion of Ukraine. There really are certain events you cannot control in undertaking a project like Sunset House! But the results of all the paving, road and block work is looking great.
There was also a lot of work being done inside the building and pressure was on timewise, because of the delays with Flooring installation. Projects that had planned to be done after the Flooring, had to be started before and now needed to be finished and out of the Building before the Flooring Team finally arrived and needed a clear space and empty building.
This impacted the Fire Department Work and the installation of 31 fitted Wardrobes. Along with the never-ending challenge of painting!
The Fire Specialists did well, and finally managed to get eleven Fire Hydrants installed throughout the building. Virtually all their internal work is now complete, and the remaining task is with the external Fire Pump house which will be finished in July.
The Joiners also did a fantastic job which we are all really pleased with. Last year we had two companies looking to do the job and we chose the one we knew better, as they are from Tileagd, and the owner had their child in our Nursery. Small world, but there was a genuine desire to help us out. See what you think.
They were told we needed them finished with installation before the Flooring was fitted. They said they would and sure enough, they are finished! And I am extremely grateful for their commitment and relieved there is still integrity in some areas of the Romanian Construction Industry!
The company has done a truly excellent job. So much so, that when the Flooring is completed, they will be back to build and install more Storage Cupboards needed throughout the facility.
Painting has been a continuous job for over a year now, having started with Mission Teams helping to Prime newly plastered walls, then apply undercoats and a first topcoat throughout the building. Applying the final top-coat was left until the majority of interior work was done to avoid creating too much dust on new paint.
I wouldn’t say we’ve been totally successful at avoiding dust, but we have tried our best and overall, it was a good strategy on logistics to save that final coat of paint as late in the day as possible and with 90% of interior work done, we did ok in the end.
But it has meant a lot of painting and without sufficient Mission teams to help, Luke has turned his hand to a lot of painting and done a superb job in all areas. Helped along the way with some hard-working and enthusiastic Mission team painters who I’ve been proud of in all that has been achieved.
The main areas remaining to be tackled are the Stairwells at the north and south ends. Luke just about finished the Middle Stairwell by the end of May. The final painting will now be completed around the Floor installation or once that’s completely finished in June.
Maybe we will have some Painters to help amongst our Mission teams in June and July!
I had hoped to be bringing you pictures and updates on the FLOORING installation that we have been anticipating for many months!
Flooring has been an ‘on/off’ situation since last October and has become a major stress for sure. However, I believe the wait will soon be over as Derek Brothers now plans to leave Northern Ireland on Saturday (June 1st) and other members of his Team will fly into Budapest on Monday, June 3rd. Hopefully by Tuesday morning, they will be on site and able to start installation at long last.
It is exactly a year since we purchased the Medically Approved Linoleum and all that time it has been stored in a warehouse in Northern Ireland, waiting for Sunset House to be ready for installation. Similarly, a Generator we purchased that is urgently needed has been waiting to come over to Romania with the Linoleum. Hopefully in the next few days, all will be here, and the real work can begin.
But after a year of waiting, we can manage another few weeks and I look forward to reporting news on the ‘finished job’ with lots of pictures, next month.
I continue to thank you for your amazing interest and support for this incredible project. Please continue praying for and supporting Sunset House, by every means you can.
Sincere blessings in the Lord.
Kevin D. Hoy