Sunset House, Cihei: Update & Gallery, March 2024
The Grand Official Opening of Sunset House, gets closer by the day. Actually, as of today (March 1st), we have 228 days before the real Celebrations and Thanksgiving begins.
As we complete nearly two years of construction, having broken ground on April 3rd, 2022 we are overwhelmingly amazed at all that God had done these past 24 months.
What was most certainly a ‘God Sized’ task has been guided and provided for by the Lord Himself. Miracles have been seen, once again, in enabling the Smiles Foundation to fulfil a Call we received to meet another need in the Romanian County of Bihor.
Now, the Main Construction is complete and the exterior work is about finished. Much of the work in recent weeks involved finishing processes along with plans and preparations for the major furnishing of the entire Facility.
The next huge undertaking that is set to start around March 18th, is the installation of the Clinically Approved Flooring throughout the facility. 2,100 m2 (approximately 22,600 sq.ft) is set to be laid by Derek Brothers and his team from Moy, Dungannon in Northern Ireland. Before that could happen, we have faced various issues of criteria to be met, before work could begin.
The building interior needed to be dry and that had required the under-floor heating to be on since January, but we are delighted to see the concrete floor completely dry now.
The special feature of Internal Gardens were causing us a small problem with damp penetration through to the fringes of the Corridor floors. With 5 large Internal Gardens, the damp concern was quite major.
Professional assessment suggested we should get the Gardens Insulated, which would stop damp penetrating through. At an additional cost of £3,500/$4,375 we hired in a specialist contractor, who has done an excellent job and we are confident the damp penetration has been stopped.
We are also anticipating the entire floor area on both levels will need Levelling Compound applied and fully dried before Derek and his Team start their work. So, to be fully confident of being ready for the Linoleum installation, Floor Levelling is expected to start by March 1st and be completed with 7-10 days. Another extra cost of £10,000/$12,500 but the finish will be so much nicer for the expensive linoleum. The investment is well worth it. 
Whilst during the past year, Mission Guests have helped tremendously with the huge Painting challenge in Sunset House, certain areas were difficult for Guests to help with and somewhat unsafe when it came
to high stairwells, so we planned on using professional painters from Romania. We were blessed to have some financial support from a lady in Scotland who was unable to come on a Mission Trip, but instead donated the costs of the trip for us to employ a painter who would be able to do what she would have helped with.
So we duly employed a local Painter, who was delighted to have the work, and now we have three major stairwells finished for banisters to be installed before Flooring starts to be laid.
Inside the Building, Suspended Ceilings continued being put up and in other rooms, solid plasterboard (dry-wall) had to be done. It’s been a huge job, but the team is about finished with just a skim plaster to finish off on some ceilings.
And then they need painting!
Another huge job has been the Electrical Work both inside and out. When the under-floor heating was turned on, we discovered the Master Generator was insufficient, so a new one had to be Ordered at a cost of £10,000/$12,500 – that is now ready for delivery and installation.
Large Electrical Control Panels were also being connected this past month, so endless cables are starting to look a little tidier as they get connected to Master Panels.
The Heat Pumps have been a headache waiting for them to arrive from China. Initially due December 14th, we have now been told they are at the Bors Border, waiting to clear customs and be paid for. The balance due is £15,000/$18,750 which we paid by end of February so the Pumps should finally be in Cihei on Monday and installation can begin.
Outside the Building, Safety Railings were a priority to be fitted as we have our Construction Inspection the first week of March and Safety Railings in place are a ‘must’. 
Thankfully, they will all be done by March 1st.
Finishing Klinker Tiles to the facier of Balconies and Main Entrance has been a lengthy job, but again, drawing to a close and we expect to see it done by March 1st.
As one might expect, the Building Site over a couple of years gets full of used stuff, particularly mountains of wood, shuttering and such like. A lot of that has been cleared up and the land levelled nicely by a bull-dozer we rented a week or two ago.

Certainly looking a lot better than it did a month ago and a much better surface to plan and work from as we consider Landscaping and Gardens.
All in all, we really are getting to those finishing stages. There are lots of them in such a large facility, but its good to be at the stage we are … finally!
March is going to be another busy but exciting month. All the Flooring to start installing. Teams start to come to help us with Electrical Installations. Then Plumbers in April along with Painters to do the Final Coat and by May, as the beautiful spring weather arrives, we will be working on Gardens. All so exciting to be at this stage after such a long and challenging Project.
Please consider whether you can come to help with all the work to finish the project as planned.
Please also continue to pray for the final Financial Support needed to complete everything on time.
Thank you for your continued interest and support for this incredible project. Please continue praying for and supporting Sunset House, by every means you can.
With my sincere Thanks.
Kevin D. Hoy
Founder and Chief Executive