Sunset House Cihei - update May 2023

Sunset House, Cihei: Update & Gallery, May 1st, 2023

Sunset House Donate $Sunset House Donate £

It was wonderful to return to Cihei on April 22nd and see the progress of Sunset House construction over the two months I had been gone for the America trip. At times, on such a large building, it is easy to feel everything is moving so slow and all we ever seem to be doing is building walls! But as those walls near completion forming the 106 rooms of Sunset House, along with the balconies and terraces that are part of the design, you start to realise this is 75% of the primary construction and all that is to follow will move faster than we can possibly keep up with!! A great and exciting challenge to have, for sure.

A lot of Walls have been built since I left in February. Phase One is now about ready for the roof slab to be poured which we will see completed during May. Phase Two isn’t too far behind and again there is every possibility of seeing the entire roof slab poured by the end of May. We pray for good weather and a healthy workforce to make the objective possible.

A lot of concrete has also be poured this past month, providing the equivilent of a Roof Ring Beam on Phase One and more Support Columns for Phase Two.
Sunset House progress

Sunset House progress
We also had two more flights of stairs concreted in, making three in all, but the biggest is around the Elevator which is a really wide staircase at 2 metres (6 feet).
Sunset House stairsSo, April had been a busy month, but the final 10 days were extremely busy and productive as several construction teams got to work on their areas of expertise within the building.

We had plasterers undertaking their ‘first layer’ of plaster over the brick. An amazing machine plastered rooms faster than I’ve ever seen!
Sunset House plastering
Sunset House plasteringWe also saw the Underfloor Heating System begin installation. Once again, no other Smiles Project has installed 100% underfloor heating, so it has been most interesting to see the process completed in the first 5 rooms and one long corridor.
Sunset House - underfloor heating
While Plastering and Heating Systems progressed, Electrical First Fix installations continued into Phase Two ground level.
Sunset House electricsAs I trust you can see, a lot of activity is being undertaken each and every day. On this basis, we anticipate being on schedule for ‘Construction Special’ Mission Teams to be able to start their work, as planned, from June 17th.

It may even be possible for some earlier teams in May or June to take a paint brush and roller to start the huge task of covering all that Plaster! But we shall see whether that proves possible in our update next month.

For sure there will be plenty to report and hundreds more pictures to choose from to show you what is happening. But nothing is better than being here and seeing it for yourself. I speak from experience having seen lots of pictures while I was away for two months, but nothing was as good as seeing the site and progress for myself when I returned to Cihei on April 22nd.

Don’t leave it too long before you come and see for yourself!

We continue to be greatly encouraged by God’s Goodness in provision of significant funds, but we continue to need God’s Provision towards the Budget for this huge project. Please continue to pray for us to be able to meet all the obligations coming up in the months ahead and do help wherever you can with a special gift for Sunset House.

In May 2023, we have Financial Commitments of £191,617 ($229,940) payments to make.

Whether Donation, Grant or a Loan – all is helpful, appreciated and significant, whatever the amount might be, to enable us to maintain our payments to all contractors to ensure the schedule for each critically important stage of this building is met and respected by all concerned.

If I can answer any questions for you, please just contact me by e-mail or a message to the Smiles Office. I’ll get back to you as quickly as I can.

I greatly look forward to sharing next month’s update.
Sunset House progress

My sincere thanks for your interest and support for this incredible project.
Sunset House Donate $Sunset House Donate £

Kevin D. Hoy
Founder and Chief Executive
The Smiles Foundation

kevin@thesmilesfoundation.org


Link to previous Sunset House Reports

Email Newsletters with VerticalResponse