Sunset House, Cihei: Update & Gallery, May 2024
The Grand Official Opening of Sunset House, gets closer everytime I look. Actually, as of today, we have 164 days before the real Celebrations and Thanksgiving begins.
Whilst there are so many aspects yet to be completed or in some cases even started, we are truly amazed at what God had done during these past 2 years.
There have, of course, been many frustrations and challenges along the way, as we expected with such a large project, and there will be many more to face before we are truly finished, but when plans and people come together, with a common vision and desire to serve, things happen.
As might also have been anticipated, as we draw closer to the finish line on various jobs, we come across an equal number of snags that constantly require attention and action. Too often that attention and action from certain contractors we have employed is slower than a ‘snail’s pace’. All of which can make life, very frustrating indeed!
In such situations I have learnt, when others don’t see the urgency you do, press on with something you can do that will be beneficial and satisfying to help compensate the frustrations of inactivity from others. This is what I have tried to do this past month.
First thing in preparation of other jobs planned, was to move the Storage Containers we use that we initially moved before Breaking Ground for the Building in April 2022. Now they needed moving to a new location, which I trust might be their final ‘resting place’ for the future.
Big heavy Shipping Containers, some full of heavy supplies, needed moving across our property to a new location. Four of them in all, plus a small Workshop!
Here’s a 60 second video of the exercise: https://youtu.be/rrKrBJWzoz0
Finally, we had our 4 Storage Containers and Workshop Container neatly in their new position.
Getting the Containers moved was very important as the next day, we had 15 mature trees arriving. Ranging in height from 7-10 metre (20-30 foot) this was designed to create a visual screen for the view from the North Lounge across the valley and between the Mission Centre and Sunset House at the South end.
Another big job and surprisingly expensive when buying mature trees! But they look super!!


It may take a few years for the full impact to be seen, but I believe the basis of what we need is now in place.
During some beautiful April days, with sunshine and 25C (80F) tempertures, we made the most of the opportunity to get some outdoor work done.
With expert builder, Tony Farquhar volunteering with us for a week, he took charge of installing two urgently wanted Water Tanks for different purposes. A 5,000 litre (1,430 US Gallons) tank was for the Fire Department Water Storage and needed installing next to the Fire Pump House.
The 10,000 litre (2,860 US Gallons) Tank was to collect rain water from the Sunset House Roof, so we could recycle it for garden watering in the hot dry summers and even car washing rather than using fresh metered water from the City.
Photos below show preparation for the Fire Department Tank. With a deadline of Cement arriving at 6pm for pouring !!
Then the Recycling Water Tank 10,000 liters / 2,860 US Gallons. A big tank! Quite a large hole!
Inside the building, plenty was happening also. From arrival of the first Mission Team, a brilliant team from Scotland, Cleaning was undertaken like I haven’t seen before. So much effort and sincerity of spirit was put into such a long, tough and laborious job.
Then I requested a staff day, when Staff could volunteer to come and do a day of cleaning. Again, they did a great job with a great attitude to doing something ‘different’ to their work at the computer whether Social Workers, Managers, Administrators or Accountants. All did a great job cleaning!
I was also delighted to see the first of the Internal Doors being fitted in April.
They started to show another dimension of a finished process. There are still Trims to be fitted and painting to be done around the doors, but it is so nice to finally see doors hanging and glass fitted.
As reported last month, as a result of the delays experienced with the main Contractor, the floor installation has been delayed several times. Ahead of the Sensory Room being fitted and the Heated Water Bed in the Physiotherapy Room, linoleum had to be laid.
So, we managed to source some linoleum in Romania and contracted with a Romanian Fitter to do the job. And a very nice job they did, much to the delight and relief of John Montgomery, designer and installer of the Sensory Room.

Whilst we delight when any job, of any size, gets completed, we realise there are still several BIG jobs to face and undertake at some point soon.
One of those jobs was the Block paving around the Building, some Patios and eventually the North Lounge Decking area which is now being done in the Block. At some point, when financial support allows, we will start the Car Parking Area which is planned for 30 cars covering staff and visitors. The cost of the project is over £34,000 / $42,500
I took a deep breath and committed to the first stage to see how it looked and how this new contracted team would operate. I have to say, I am very impressed with their attitude to work, quality of work and integrity of operating. It has actually been a very refreshing experience after so many nightmare situations with Contractors over the past 2 years.
Hard to do justice by pictures, which is why I recommend you come to see it, but the finish will be quite superb. And even the process doesn’t look too bad!

There will be much more to see next month, so be sure to check back and even better, come and see it for yourself, on a Hands-On Mission Trip to help complete Sunset House, Cihei.
I continue to thank you for your amazing interest and support for this incredible project. Please continue praying for and supporting Sunset House, by every means you can.
Sincere blessings in the Lord.
Kevin D. Hoy
Founder and Chief Executive
The Smiles Foundation