Sunset House, Cihei: Update & Gallery, November 1st, 2022

Sunset House Donate $Sunset House Donate £

An incredible month of work is evident on the Sunset House site here in Cihei. I don’t think we could have imagined making such progress, but everything has been blessed to allow efficient and fast development of this amazing project.

The site has been at the height of activity everyday during October but the results speak for themselves and I am delighted to share with you the details and some pictures behind the Headlines of Progress this past month.

Sunset House progressWith the size of this project, we have basically split it into two phases on about a 60/40 split.

The first phase, about 60% of the building, was ready to start laying bricks 30 days ago. Having placed the order for over 60,000 bricks, the trucks started delivering them on Friday, September 30th. By Saturday morning, October 1st – walls were starting to appear!

And those walls kept growing, and growing, every day of October, so that by October 31st – virtually every wall of the ground floor of phase one is constructed! What an amazing sight it is.

With a skilled team of workmen on building the walls, another team continued the preparations of the foundation footings for phase two. Just as we had seen with phase one, the intricate work for the foundations was detailed and time consuming, but the team were racing the ‘weather clock’ and wanted to be seeing concrete poured on the foundation footings as soon as possible, so they could work towards the Slab being poured before the beautiful autumnal weather ended.Sunset House ProgressThe warm, sunny days of an October, none of us could remembers the likes of, demonstrated God was on our side, and the constructors wanted to honour that by having everything ready as close as possible to the end of October. After very careful work, the first Inspection was arranged for October 21st and at 11am, the papers were stamped and signed. We had passed the inspection and in less than 3 hours, concrete was being poured! By 7pm – all the foundations were complete, and an immense sigh of relief was heard along with our thanks to God echoing around Cihei.

As with phase one, Drainage and Sewage Pipes needed installing before Soil filled in the mass areas, with stone on top of soil and then compressed. As I write, Insulation is being laid, then the damp proofing membrane will be spread and finally the metal reinforcement. When all that is complete, which we pray will be by Thursday November 3rd, we will be ready for concrete to be poured again.
Sunset House walls and inspection
Then it will be more of the same. Walls will start to be built on Phase Two – joining the work of Phase One, but it won’t be long before the walls are at First Floor level when supports will be in place for the floor to be poured with more concrete!

There is so much activity and such progress that I want to share the excitement with you. For that very reason, I produced another Video update this month even though it’s only a month since the last one. However, I hope you will take time to enjoy the signs of progress for Sunset House, Cihei.

Update as at November 1st, 2022 

As I emphasise on the Video, the pace of work is incurring huge costs, as we expected when accepting the major Construction to be done in 13 months, rather than the originally planned 36 months. However, to do our best to avoid those ever-increasing cost of materials that could have sent the budget beyond our means, we went with the 13-month construction contract.

Now we must do everything we can to meet our obligations on the construction and essential associated materials to enable the contractor to fulfil his part of the contract by May 2023.

It is very exciting to hear from the Smiles Family of plans being made to support the project financially, but we need a lot more to join the Visionaries and Enthusiasts to see these obligations met in full. Please contact me if I can answer any questions or help with any plans you have for partnering with us in the building of Sunset House, Cihei.

Thank you for joining us to make this dream a reality.

Sunset House Donate $Sunset House Donate £

Kevin D. Hoy
Founder and Chief Executive
The Smiles Foundation

kevin@thesmilesfoundation.org


Link to previous Sunset House Reports

Email Newsletters with VerticalResponse