Sunset House, Cihei: Update & Gallery, November 1st, 2023
As you may recall from the update last month, sealing the roof had become a critically important job to see completed. Thankfully, by the end of September, the first complete layer of Bitumen had been laid across the entire roof. This was an important stage to reach, but not the final stage of sealing and waterproofing the roof. A further layer of bitumen was to be laid and that needed a completely dry period to ensure no water or even moisture was trapped between the bitumen layers. We waited and we waited, Sunset House has certainly taught us patience!
On October 30th, as we were enjoying some beautiful autumnal sunshine with temperatures above 20C (70F), to our delight, the men returned to complete the roof. Our hope is, by the time we wrap up our this update, the Roof will indeed be finished and completely sealed with Bitumen by close of work on October 31st. Here is progress on the 31st!
We praise God for finally having a sealed building which we trust will now be fully waterproof, but I guess that test will come with the first rain! But we have faith!! Actually at 6pm on October 31st we have a thunderstorm, so we’ll know the success of water-proofing in the morning!
As we have had for many months now, we still had plasterers all around the building, inside and out.
The amount of plastering and the length of time it has taken, is a constant reminder of just how large Sunset House is. At times we have had up to eleven men plastering inside and at the same time, up to six men plastering the exterior.
It is so thrilling to report that as of October 31st, virtually all the interior plastering is complete and now the team will spend a few days making repairs and minor adjustments, before the entire plastering workforce move to the exterior.
There is still plenty to be done outside!
But as this current spell of beautiful weather is unlikely to remain for very long, I’m sure the team will be getting to finish the exterior as soon as possible, conscious of the onset of winter and much cooler days, and most likely, much wetter days.
Interior work was continuing in every corner of the building.
In the final phase of construction – Phase Two Upper level – there was important work to be done in completing the underfloor heating system. This was done during October.
Miles more tubing covering the floor, after polystyrene insulation was put on top of the concrete floor and then a plastic membrane, before the heating pipes are laid and then, covered by Floor levelling cement! An amazing system, which we trust will be very efficient and effective.

Heating Pipes covered and floor levelled on final Phase Two of the facility.
In October we had yet more exciting major aspects to the building completed and it really made for an exciting month of progress. Two major aspects to report on.
Firstly, we had been waiting since the first week of June, when the Lift (Elevator) was delivered from Spain where it was manufactured. When we contracted for the Lift back in November 2022, the Contractor told us to have it ready for installation in June. Well, things didn’t work out quite as timely as the contractor hoped, so it was October 12th, 2023 that we finally got the 29 boxes and packages that had arrived from Spain in June, out of our Store and into the Sunset House large reception area, ready for installation.


And then the highly skilled and technical task began – Installation.
I was so impressed and intrigued by how a lift/elevator is put together!
Put together like a 10,000 piece jigsaw, I admired each day for the two weeks of work, how it was coming together. But finally it did, and is now only waiting for the protective tape to be taken off the bright gleeming stainless steel. But that won’t be until sometime next spring!
Sunset House Lift/Elevator – Lower Ground Floor goes to upper level and Roof!
The second major achievement was seeing the Frames and Windows installed at the entrance of the Building – lower and upper floors. This was critically important to help seal with building, making it ‘wind & watertight’ as the interior needed to dry completely for Painting and Flooring. But finally it was done. Frames were installed October 20th and the Glass fitted October 25th. And how good it looks and feels to have the entrance finished.

While all the Contracted teams were working, we also had our wonderful teams of Volunteers working on Sunset House as part of their Mission Trip. And we had some fantastic workers this past month, as indeed we have been priviledged to enjoy all year.
More Painters who did an amazing job.
And Cleaners, including taking Tape from Windows Frames. (Such a laborious job!)
We also had delivery of ceramic tiles for all the Balconies and Patio’s in the Facility.
Lots of Tiles but we had another Trustee out on the Mission Trip who turns his hand to most practical challenges.
Ian Steenson, and his brother Billy, were with us for a week in October and had a very busy few days!
They managed to complete 4 Balconies, each requiring about 100 tiles to be laid.
Tony Farquhar on the Mission Trip a week earlier had started the process with one Balcony having fitted 12 interior windowsills in all Phase One lower ground Bedrooms. Plenty more to be done, but a fantastic start for sure.
As is featured and detailed in my main e-mail this month,
The Smiles Foundation » From Kevin Hoy, CEO & Founder, November 2023
we have great need for many volunteers to come from March 2024 through May to get involved with skilled work to complete our challenge of having Sunset House ready for staff and residents to start arriving by June 1st, 2024.
It seems another one of those impossible deadlines, but with enough people inspired to help, it can be done, to the Glory of God and to provide a huge blessing for so many people here in Romania.
If we keep our eyes fixed on Jesus, nothing is impossible. He has promised to complete the Good Work He began.
Last week, after a long day of thinking about all that was needing to be done, as I walked from my office to the Mission Centre, I saw the most incredible Rainbow arching right over the property, creating a full arch over Sunset House – it was absolutely amazing.
I’m not much of a photographer, but I grabbed my phone and took a photo of the incredible sight.
As I took it and looked at the result, I felt God speaking to me and reassuring me of His Promise, that this Project was His Project, we are just guardians and executors, needing to listen carefully to all His Plans and Instructions to be assured of everything finishing in His Way and in His time.
The RAINBOW – such a magnificent PROMISE
My sincere thanks for your continued interest and support for this incredible project. Please continue praying for and supporting Sunset House, by every means you can. Thank you.
Kevin D. Hoy
Founder and Chief Executive
The Smiles Foundation