Sunset House, Cihei: Update & Gallery, October 1st, 2023
As we started the month of September, the pressure was on to ensure several critically important tasks were completed within the month. Although several of those tasks would be rivalling for top spot of ‘most important’, I felt that the roof was my primary concern so we would ensure ‘sealing’ the building from damaging rainwater. All through the summer, even though a hot one, the thunderstorms would bring heavy rain, and time after time, we had floods to contend with inside the building. A lot of that was from the roof, a huge area of approximately 1,800 square metres (nearly 20,000 square feet) and it took on a lot of water during a heavy thunderstorm. Until all the drainage was completed, that water poured through the concrete roof and joints waiting to be sealed. It was a constant nightmare we faced after every rain fall.

Finally, the Construction company were ready and the huge task of sealing the building’s roof started with Insulation across the initial cement roof.
On top of the insulation was a plastic membrane, laid across every inch of the insulation before the final pour of concrete on top.


Still not done though, as on top of the cement, was a first layer of Bitumen which begins the waterproofing process.
And the entire Roof with first layer of Bitumen complete.
As impressive as that looks when covering the entire roof, there is still a second layer of Bitumen to lay and that should be completed in the first 7-10 days of October. We look forward to that point being reached, but already we can see, that with everything done on the roof so far, 99% of the roof is indeed waterproof. A few drops coming through that could be due to water trapped between the initial cement and insulation. A few small drill holes will drain that and when the second and final bitumen coat is laid, we can be 100% sure that not a drop more rain will be finding its way into the building.
We will have a week or so to test that before the Painting begins on the upper level of Phase One and Two with our Mission team starting October 14th.
Below the roof, inside the building, there was a tremendous amount of plastering to be done. When we look at the number of plasterers here week after week, it’s hundreds of hours of constant plastering and you really start to realise how massive this facility is.
However, three separate Plastering Teams were on site virtually every workday of the month.
One team continued the finishing work after doors and windows were fitted. That team then moved onto finishing the inside of the Interior Gardens. I suppose the inside of our interior gardens is technically the ‘outside’ as our Interior Gardens are open to the elements, so the finish to the walls is as the outside of the building – Insulation, Plaster, and Finishing Render. Team One has been working on the first three Interior Gardens.
Team Two worked tirelessly on first fix plaster on Phase Two upper level. This was a big job once first fix plumbing and electrics were done. But they managed it and after a long full day on Saturday September 30th, they were complete and finished their contract on Sunset House accordingly. They will be back to Cluj on Monday!
Team Three had been working on the exterior, second Phase and doing a nice job for sure. Our concern for getting the interior finished and ready for paint, meant a week or so ago we pulled all hands inside the building, so Team Three started the final plastering process on Internal Gardens 4 and 5. Once they are finished, the team will probably move back to the exterior to continue the insulation and plastering job.
As Plasterers finished the upper level of Phase One, the plumbers were ready to move in to begin installing the Underfloor Heating which is currently a ‘work in progress’. With plans to have that finished in 3 or 4 days, the Floor Levelling company will then be back to cover all the heating tubes and provide us a finished floor.
Over the next couple of weeks, the cycle we are quite familiar with now will continue. When the floor levelling is complete in Phase One, plasterers will return there to do their final finish in readiness for painting from October 14th.
The plumbers will have moved to Phase Two upper level for Underfloor heating, followed by the floor levellers and then, you guessed it, the plasterers to finish off ready for paint.
Having planned the construction in 4 stages of Phase 1 lower, then Phase 2 lower – followed by Phase 1 upper and finally Phase 2 upper – with the roof being completed somewhat separately while all the interior finishing work was being done – it has been a rather repetitive process for each Stage, but for sure, we have got to know much better the process and how best to plan it after the Lower Level was complete. But the entire job became much easier and better to control once the Roof was worked on and now it is virtually complete, we can see the rest of the building following on to completion quite quickly.
With more large Window frames being fitted the first week of October, we will see the final elements of sealing the building to Wind & Watertight complete, and our major objective of achieving that both for Painting and Electrical work in October, and then the laying of Linoleum Flooring in November – could see the building at an exciting stage and just where we wanted it by Christmas. That might well be the best Christmas present I could have!
After a nice rest over Christmas and New Year, we will be making plans for more interior finishing work as volunteers can come to help from January onwards. There will be a lot to do and a variety of skills will be needed, which I sincerely pray we will have many willing helpers to come and help us in these finishing stages.
There’ll be a substantial number of bathrooms to furnish installing Toilets, Showers and Basins.
There will be 2 walls in every bathroom to have sheet cladding fitted. There will be sliding doors to install on the fitted wardrobes in 30 residential rooms. If not completed in October, there will be Tiles to lay on Room Balconies, Patios and Walls around the entrance. There will be numerous electrical 2nd fixes to complete, including Lights to every room not managed to complete in October.
So many tasks and a lot of willing hands to help are needed.
If you can consider helping for a week or more on a Construction Special Mission Trip, between January and April, let me know for which area of work you could help with and we’ll fit you into the master schedule of finishing Sunset House, Cihei.
In April, we will need landscapers, gardeners and outdoor helpers to see the Grounds of Sunset House prepared and to install the Patio Roof Gardens, which will be something very special indeed. Plan to come and be a part of something very special.
My sincere thanks for your continued interest and support for this incredible project. Please continue praying for and supporting Sunset House, by every means you can. Thank you.
Kevin D. Hoy