Sunset House Update

Sunset House, Cihei: Update & Gallery, September 1st, 2023

Sunset House Donate $Sunset House Donate £

August has been a very hot month with temperatures around 37.5C (100F) for much of the month. Hot weather during construction work is hard, especially when much of the work is on the roof, with no protection from the extreme heat.

After the challenges and stress of a difficult July, the new crews appeared to settle in quickly and were able to pick-up where others had left off, and we could be a little encouraged that progress was being made, once again. Slow, but positive and at this stage of proceedings, I take the slow but positive route, willingly.

Most pleasing for the start of August was having the entire Roof Slab poured. It was great to see the entire building covered and to begin planning for the next stage of important work.
Sunset House Roof slab poured

There was some critically important work to complete on the roof and the departure of the initial crew in July, had added a few more weeks to the delayed schedule.

But the new crew got to work and soon the elevator shaft was being built up and shuttering built ready for more cement pouring. Likewise, the stairs around the elevator were completed all the way to the roof. Finally the enclosed canopy on the roof where the elevator arrives had to be built. A similar but simpler enclosed area was to be built at the other entrance to the roof – the west stair well – which was done, and both areas completed ready for cement pour on August 31st.

Sunset House lift shaftAs this addition to the structure starting to appear on the horizon, we began to realise the impact of the size of this facility was not finished yet. Coming down the Cihei Hill (which some of you will know well) started to show this huge towering building across the valley which surprisingly, hadn’t been quite so obvious before .. now it was!
Sunset House stairwell

We were blocked from accessing the roof for a couple of weeks due to scaffolding and support beams up and across the stairs. Earlier in the month, a couple of Mission Team groups had access to the roof and just marvelled at the view and as I have said before, it is pretty spectacular!

Unfortunately, the last couple of teams could not, but once the cement being poured now, is dry and supports removed, I’m hoping more of our guests will be able to go to the roof and be inspired as I am, every time I go up top. I think I am safe to say, those visiting in October onwards will have full access to the roof and be able to take it all in, at their leisure.

Another major process on the roof in August was the starting of ‘sealing’ the roof. This is done with insulation on top of the concrete slab, then a membrane sheeting across all the insulation. On top of the plastic membrane, another layer of concrete is poured. This has been accomplished so far on about 65% of the roof. In early September, the roof-top structures around the central stairs and elevator along with the west stairs will be completed. At that point, we will immediately look to complete the final 35% of the roof with insulation, membrane and concrete. Once that is completely dry, the entire roof in one pour, will be covered with bitumen (like asphalt) across 100% of the roof which at that point, will finally be ‘sealed’. Pray with me that we will meet the revised deadline for this of September 15th.


‘Sealing of the Roof’

Insulation on top of the Concrete slab

Insulation on top of the Concrete Slab

Plastic membrane

Plastic Membrane across the Insulation

Levelling the concreteLevelling of the Concrete above the Membrane

Sealed roof awaiting bitumen pouring

Sealed Roof awaiting final Bitumen Pour


Of course, there was also a lot of work progressing inside the building, not least due to constant Mission Teams, coming to serve where needed and for sure we needed help in Sunset House, Cihei.

Having had teams in earlier months help with Priming the Walls and Undercoating as much as possible, August Teams were able to start the happy process of painting Walls in residential bedrooms with the final coat of Blue paint.
Blue paint

And also the Office and Ground Floor Activity Rooms got their first top coat!Office & Activity room painting

Electricians in the Team continued the ‘endless’ task of wiring in Wall Plugs and Switches.
Electricians

We also moved into Phase Two lower level which meant Internal Gardens were soon to be getting their Frames installed. That meant, you guessed it, we needed more of the Tall Trees that need moving in before the Frames are installed, so Maria and I were off to the Tree Company once again. As usual, there was a wonderful selection and we have been so blessed to have a good company right here in Cihei from where I expect to buy all the trees and landscaping plants we’ll need for the entire facility. We may have only purchased 15 so far, but by spring next year, it will be hundreds, and I think the manager at the company will have done very well, taking good care of us in those early days, when the strange English man turned up asking for 5 metre trees! It will pay a good dividend for him down the road!!
Trees at Sunset House

And today, August 31st, the company are here installing the Frames, so the Trees were in place, just in time.

Frames installedThe whole of the upper level was the height of activity all month.
Plastering teams were everywhere we turned!
Plastering

Phase One Upper Level – 1st Fix of Plaster          Mixing of Plaster a full-time job!
PlasteringThe final Skim of White Plaster applied               Room Plastered – Ready for Painting!

For sure, all 12 Bedrooms and bathrooms will be ready to Paint with October Mission teams!!
Meanwhile, Builders are finishing the Walls in all the Rooms on Upper Level of Phase Two. Plasterers will be moving in there as soon as Plumbers and Electricians have completed their first fixes.

Back to the Plasterers, we had a third team arrive who started the exterior Insulation and Plastering of Phase Two.

Exterior insulation

Finally, the ‘cherry on the cake’ for Plasterer achievements in August, was the start of the final finish render to exterior Phase One, which I must say, is starting to look rather special!
Exterior plastering

As we move into September, I feel the clock is ticking louder for all concerned.

Deadlines, even revised deadlines, are getting closer and the knowledge of the serious implications on subsequent plans if those deadlines are not met, adds a great deal of stress but on a positive level, also adds to our daily prayer life.

So, what is causing the increased prayer life for calm and clarity in the coming weeks?
Well, many important tasks are to be finished:

1. The Elevator Shaft and Stairs to allow Installation of the Elevator in September.
2. Completion and full ‘Sealing of the Roof’ to ensure the building below is finally Watertight.
3. Upper Level to see Plastering, Underfloor Heating system, Floor Levelling – ALL FINISHED by October 16th.
4. All Exterior Doors and Windows installed in September so the Building is finally ‘watertight’ and can begin the Drying Process for Flooring to be laid in November.
5. Levelling of ALL Balcony Floors ready for Block Work to be laid when skills available.

If we can pray these tasks to completion, I’ll be delighted and will be happy to detail the next list of priorities next month! One thing I know we will need for October, are lots of Hands-On support, especially with painting as I can honestly say, it is hard to imagine how much painting is needed and we want it done by end of October, in the hope the Flooring can start to be laid November 6th.
If we get that done by December 1st, I promise we can take a month’s rest, or at least less pressured, while we celebrate the Lord’s Birth and then be ready to face all that will need to be done in the new year of 2024 … the year Sunset House, Cihei is due to open!

Can we do it? With God on our side, of course we can. If you can help any time in October, from 1st – 31st, we’ll be ready for you. E-mail me or call the Smiles Office for further details.

There has been a lot to take in with this month’s update. If you would like the easier version, you might enjoy the Video I prepared to summarise progress to date. I hope you enjoy:
VIDEO LINK 

My sincere thanks for your continued interest and support for this incredible project. Please continue praying for and supporting Sunset House, by every means you can. Thank you.
Sunset House Donate $Sunset House Donate £

Kevin D. Hoy
Founder and Chief Executive
The Smiles Foundation

kevin@thesmilesfoundation.org


Link to previous Sunset House Reports

Email Newsletters with VerticalResponse