Sunset House, Cihei - Update and Gallery

Sunset House Aerial view

Sunset House, Cihei: Update & Gallery, September 2024

Sunset House Donate $Sunset House Donate £

Due to numerous commitments in the final week of August, I am preparing this Update early, adding to it day by day to give you an up-to-date summary of where we are at with just 41 days to go!

Yes, as of September 1st, we have 41 days to the Grand Opening and to say we’ve a lot to do, is something of an understatement!  For sure, the clock continues ‘ticking’ for the Sunset House, Cihei Project.  But on October 12th & 13th – what an amazing weekend of Celebration and Thanksgiving we will have as we focus on what our God of Miracles has done over the past two and a half years.

It has been a challenging month on achieving progress with Sunset House, as August inevitably encounters ‘peak holiday season’. Many contractors have been away, several suppliers and manufacturers closed for a couple of weeks, so a little frustrating when we hoped to see more achieved which proved impossible due to scheduling.

However, we pressed ahead with things that could be done and made good progress on several issues. We spent a lot of time researching options for equipment needed and Maria and Simona even took a day to visit Timisoara for shopping at various large Furniture Stores.
Must have been tough for them! But as they told me, “someone has to do it”!

Just as well they did, as we discovered in some cases, items they wanted had a 4-6 week delivery wait, so getting it ordered around August 9th, means we should have all we need by September 20th and then the fun begins getting everything in the right rooms, nicely organised.

So, while a lot of researching and ordering was being done, we did manage to ensure actual work on site continued where possible and I am delighted with the progress made in those areas.

Let me walk you through the sort of major tasks that were undertaken this past month, some started, some continued from the previous month and some finished. That’s always a really nice feeling!

Let’s start with the Flooring. If you follow my Updates each month, you will know that back in June this year, Derek Brothers from Moy in Northern Ireland was finally able to get here and start the huge job of laying the Medically Approved Linoleum throughout the Facility.
FlooringVarious issues have meant Derek has made 3 trips back and forth but his final trip for the Flooring had him arriving August 25th and he anticipated less than a week of work to finish all that was needed, which was primarily sealing joints with Hot Welding Rods that were difficult to source here in Romania, so were sent from Northern Ireland. Since Brexit, the 2-day delivery service became 10 days, hence further delays. Finally, Customs released the box of material, and UPS delivered it, so Derek could make plans to come.
Once here, he pressed on with his normal unrelenting 15-hour days and sure enough, within the week, the job was completely finished.
FlooringThank you, Derek Brothers, for generously supporting the work of the Smiles Foundation by doing the entire fitting of the Flooring, with your crews, all voluntarily and at no cost to the Foundation. We truly appreciate your support very much indeed.

One job that had been waiting many months for the Flooring to be finished, was installing the Toilets in every bathroom. Not only 30 in residential rooms, but 5 others in general bathrooms for residents plus 5 staff bathrooms, with those also needing Vanity Units. Derek didn’t want any of these done until he had finished laying the Flooring, as cutting around all those units would have doubled his work time. So, only when flooring was finished could we start with all the bathroom fittings, but they are well on the way to also be finished now.

Toilet fitting
Again, with linoleum laid in the Corridors and Stairwells, we were able to start the huge task of installing Banisters and Handrails throughout. Our friendly Joiner, Dacian, set to work and made good progress with banisters of some 250 linear metres (820 linear foot). Then he started on Skirtings for Entrance Areas, Corridors and Lounges. Even more at 500 linear metres (1,640 linear foot)!

Banisters
Outside, we had been attempting to source a supplier of Metal Supports & Covers for the Heat Pump Pipes that since we moved them to the Roof, were not covered under the original contractor. His quotation for the extra material and installation was rather excessive, but thankfully we had an old contact who we worked with 20 years ago, come to the rescue. They are a Metal Company owned by a Christian, who was delighted to help us. We ended up agreeing for them to do far more than just the Heat Pump supports and covers, but also Supports for the Solar Panels, Doors for the Fire Pump House and Steps.

Metalwork
They are also doing the Safety Rail around the North Patio so with a contract total of more than £10,000/$12,500 I think he was pleased to make connection with us again, after all the years.

We also needed some Extractor Fans installed in Bathrooms which required a specialist coming to drill through the Walls to create a vent.

Vent

Similarly, we needed two Air Vents drilled into the Elevator Shaft to meet Code and these had been overlooked in the initial construction. Fortunately, the Elevator Installation Company pointed out the issue and we were able to get it done, before the next inspection!

Elevator shaft

Waiting for a lot less activity and dirty dust in the Building, was our IT Consultant who was wanting to start the enormous job of installing all the cabling for Internet, TV’s, Camera’s and a Nurse Calling System. A lot of cabling for sure. I’m not sure off hand how much, but it will be an interesting statistic to obtain, as I’m sure someone will ask me the question at some point!
Cabling
But if Flaviu is around when that question is asked, or any other relating to the IT installation, Flaviu will know the answer for sure, and I’ll be happy to introduce him to the inquisitive visitor!

However, I was intrigued by the question, so I asked! ANSWER:
9,900 Linear metres / 32,480 linear feet!

Nearly 10 kilometres / Just over 6 miles of IT Cable for Sunset House, Cihei !!

Another, significant job accomplished in August, was the building and installation of the Hydrotherapy Pool for our Specialist Medical Wing – providing Hydrotherapy, Physiotherapy and Sensory Therapy.

Hydrotherapy pool

The Sensory Room was completed in July. Now the Hydrotherapy Pool installed in August. The Physiotherapy Equipment has been ordered and scheduled for delivery in September. We are moving in the right direction!

Having lived for so long with ‘empty’ rooms, knowing we couldn’t start actually furnishing until the flooring was complete, with the progress made in a number of rooms before Derek left on August 10th it meant we could start the exciting stage of ‘furnishing’, just as soon as the fitted furniture being manufactured could be installed and the furniture purchased at stores, could be delivered. In August, some of both was achieved!

Lockers in Staff Rooms on both floor levels.

Staff Room lockers

Storage Cabinets in Medical Wing

Storage in medical wing
We also had a couple of Sofa’s delivered with a lot more to come in addition to Tables and Chairs coming in September.

The soft sofas were lovely to see and test for a brief moment ….
Sofas…. but then we had the joy of seeing Curtains and Blinds installed which are mixed between the 30 Residential Rooms for various reasons.
Curtains and blindsBut all is beginning to make this facility the beautiful ‘home’ we have been anticipating.

Finally for the month of August, we returned to the Gardens, for which we had received extra help from Mission Teams to prepare for the next stage of planting. The challenge was the weather!

It was not only very hot for the team to work on the grounds, so most of the preparation was done in the morning, as after lunch it was just too hot. But that also affected the planting, as without rain or any sign of it, we had to be sure the plants could be properly cared for, especially with water, until their roots took firm hold in their new home.

But the task is in hand with some slightly cooler days, down to 33C/91F and the benefit of our new Water Well providing the care needed for new Plants without risking supply to our Cihei facilities.

GardensThere remains a lot to be done and considerable costs to be met, and time is getting short!
I pray the Smiles Family will help us finish the challenge of Sunset House. A marathon always needs a finishing sprint, and we need that now with support for Sunset House.

To finish all that is important before the Grand Opening, we have £144,109/$180,136 to raise leaving some extra, less critical issues such as the Rooftop Terrace Garden and Car Parking area, until later in the year or early next.

Without those larger, less critical items, the Budget is set to come in at £2,729,442/$3,411,802 – higher than anticipated back in 2022 but there has been a lot to contend with these past 3 years and construction costs have been impacted significantly.

I appreciate the Smiles Family immensely, for their response to the great needs we face in fulfilling the ministry, especially when such large commitments exist around Sunset House.

But we are getting there, step by step.
5.3% to finish
As of today, we are within 5.3% of the Financial Finish Line.

We pray this amount will be met by the time the Facility is due to be finished and we celebrate the Grand Opening on October 12th & 13th, 2024.

Please continue praying for, and supporting Sunset House, by every means you can.

May the Lord richly bless you.

Sunset House Donate $Sunset House Donate £

Kevin D. Hoy
Founder and Chief Executive
The Smiles Foundation

kevin@thesmilesfoundation.org

Sunset House


Link to previous Sunset House Reports

Email Newsletters with VerticalResponse